Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
78
matching recommendationsNAICS | 331 | Primary Metal Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0596 # 10 Y:2023 | 10 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $26,447 | $4,768 | Implemented |
UF0596 # 11 Y:2023 | 11 | 2023 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,156 | $2,352 | Implemented |
UF0596 # 04 Y:2023 | 04 | 2023 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $213,087 | $0 | Implemented |
UF0596 # 07 Y:2023 | 07 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $47,000 | $171,903 | Implemented |
UF0596 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $27,499 | $1,399 | Implemented |
UF0596 # 05 Y:2023 | 05 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $145,162 | $141,225 | Implemented |
UF0596 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $50,904 | $49,563 | Implemented |
UF0596 # 03 Y:2023 | 03 | 2023 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $232,670 | $300,000 | Implemented |
UF0596 # 09 Y:2023 | 09 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,289 | $25,440 | Implemented |
UF0596 # 02 Y:2023 | 02 | 2023 | INSTALL SUB-METERING EQUIPMENT | $266,539 | $15,232 | Implemented |
UF0595 # 08 Y:2023 | 08 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $1,317 | $5,838 | Implemented |
UF0595 # 10 Y:2023 | 10 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $20,697 | $4,480 | Implemented |
UF0595 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $18,931 | $25,400 | Implemented |
UF0595 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,458 | $356 | Implemented |
UF0595 # 06 Y:2023 | 06 | 2023 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,957 | $3,276 | Implemented |
UF0595 # 07 Y:2023 | 07 | 2023 | INSTALL SUB-METERING EQUIPMENT | $1,589 | $4,340 | Implemented |
UF0595 # 02 Y:2023 | 02 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $39,683 | $20,785 | Implemented |
UF0595 # 09 Y:2023 | 09 | 2023 | INSTALL OCCUPANCY SENSORS | $1,092 | $2,160 | Implemented |
GT0937 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,545 | $4,311 | Implemented |
GT0937 # 01 Y:2019 | 01 | 2019 | INSTALL OCCUPANCY SENSORS | $1,362 | $310 | Implemented |
UF0508 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,193 | $2,737 | Implemented |
UF0508 # 02 Y:2017 | 02 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,114 | $20,000 | Implemented |
UF0508 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,144 | $1,169 | Implemented |
UF0508 # 08 Y:2017 | 08 | 2017 | INSTALL OCCUPANCY SENSORS | $1,548 | $478 | Implemented |
UF0508 # 09 Y:2017 | 09 | 2017 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $3,871 | $700 | Implemented |