Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
131
matching recommendationsSIC | 33 | Primary Metal Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0596 # 02 Y:2023 | 02 | 2023 | INSTALL SUB-METERING EQUIPMENT | $266,539 | $15,232 | Implemented |
UF0596 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $50,904 | $49,563 | Implemented |
UF0596 # 09 Y:2023 | 09 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,289 | $25,440 | Implemented |
UF0596 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $27,499 | $1,399 | Implemented |
UF0596 # 07 Y:2023 | 07 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $47,000 | $171,903 | Implemented |
UF0596 # 11 Y:2023 | 11 | 2023 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,156 | $2,352 | Implemented |
UF0596 # 10 Y:2023 | 10 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $26,447 | $4,768 | Implemented |
UF0596 # 03 Y:2023 | 03 | 2023 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $232,670 | $300,000 | Implemented |
UF0596 # 04 Y:2023 | 04 | 2023 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $213,087 | $0 | Implemented |
UF0596 # 05 Y:2023 | 05 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $145,162 | $141,225 | Implemented |
UF0595 # 02 Y:2023 | 02 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $39,683 | $20,785 | Implemented |
UF0595 # 10 Y:2023 | 10 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $20,697 | $4,480 | Implemented |
UF0595 # 09 Y:2023 | 09 | 2023 | INSTALL OCCUPANCY SENSORS | $1,092 | $2,160 | Implemented |
UF0595 # 08 Y:2023 | 08 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $1,317 | $5,838 | Implemented |
UF0595 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $18,931 | $25,400 | Implemented |
UF0595 # 06 Y:2023 | 06 | 2023 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,957 | $3,276 | Implemented |
UF0595 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,458 | $356 | Implemented |
UF0595 # 07 Y:2023 | 07 | 2023 | INSTALL SUB-METERING EQUIPMENT | $1,589 | $4,340 | Implemented |
GT0937 # 01 Y:2019 | 01 | 2019 | INSTALL OCCUPANCY SENSORS | $1,362 | $310 | Implemented |
GT0937 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,545 | $4,311 | Implemented |
UF0517 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $131,032 | $232,640 | Implemented |
UF0517 # 04 Y:2018 | 04 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $21,928 | $0 | Implemented |
UF0517 # 05 Y:2018 | 05 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,845 | $9,000 | Implemented |
UF0517 # 02 Y:2018 | 02 | 2018 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $39,058 | $11,918 | Implemented |
UF0517 # 03 Y:2018 | 03 | 2018 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $20,334 | $78,376 | Implemented |