IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

50

matching recommendations
Reset
ARC 4 DIRECT PRODUCTIVITY ENHANCEMENTS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LS2009 # 07 Y:2020 07 2020 INSTALL AUTOMATIC PACKING EQUIPMENT $57,969 $120,000 Implemented
UF0560 # 07 Y:2020 07 2020 LEVEL THREE - INSTALL OR MODIFY CONTROL SYSTEM WITH COMMUNICATION AND NONLOCAL EXTERNAL INFORMATION (I.E. WEATHER FORECA $134,615 $11,004 Not Implemented
UF0560 # 08 Y:2020 08 2020 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $9,639 $725 Implemented
UF0559 # 08 Y:2020 08 2020 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL $5,262 $7,180 Implemented
UF0558 # 03 Y:2020 03 2020 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $42,983 $7,127 Implemented
CL2015 # 01 Y:2020 01 2020 MODIFY STARTUP/SHUTDOWN TIMES $7,855 $550 Not Implemented
IP0142 # 01 Y:2020 01 2020 PAY BILLS ON TIME TO AVOID LATE FEES $580 $0 Not Implemented
UF0555 # 05 Y:2020 05 2020 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $340,000 $5,859 Implemented
UD1025 # 10 Y:2020 10 2020 INSTALL EQUIPMENT TO MOVE PRODUCT $454,408 $375,000 Not Implemented
UA0234 # 01 Y:2020 01 2020 MODIFY STARTUP/SHUTDOWN TIMES $17,505 $0 Implemented
IP0141 # 04 Y:2020 04 2020 APPLY FOR INVESTMENT INCENTIVES $2,218 $2,000 Implemented
IP0141 # 03 Y:2020 03 2020 APPLY FOR INVESTMENT INCENTIVES $15,156 $10,000 Implemented
MZ0296 # 06 Y:2020 06 2020 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $100,865 $197,145 Not Implemented
MZ0296 # 07 Y:2020 07 2020 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $57,876 $199,418 Not Implemented
NC0652 # 06 Y:2020 06 2020 CONDENSE OPERATION INTO ONE BUILDING $6,086 $4,800 Not Implemented
CL2011 # 04 Y:2020 04 2020 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $7,830 $4,500 Implemented
CL2010 # 04 Y:2020 04 2020 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $14,466 $4,500 Implemented
UF0554 # 05 Y:2020 05 2020 INSTALL SENSORS TO DETECT DEFECTS $3,851 $15,420 Implemented
UF0554 # 04 Y:2020 04 2020 LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS $9,363 $0 Implemented
UF0553 # 04 Y:2020 04 2020 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $395,494 $1,875,550 Not Implemented
UF0553 # 05 Y:2020 05 2020 LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS $2,236 $0 Implemented
UF0553 # 01 Y:2020 01 2020 AUTOMATE FINISHING PROCESS $20,196 $46,226 Not Implemented
UF0552 # 01 Y:2020 01 2020 LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS $23,402 $0 Implemented
UF0552 # 06 Y:2020 06 2020 INSTALL AN UNINTERUPTABLE POWER SUPPLY $45,577 $65,793 Implemented
IP0140 # 05 Y:2020 05 2020 APPLY FOR INVESTMENT INCENTIVES $26,189 $10,000 Not Implemented