Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26
matching recommendationsARC | 4 | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2009 # 07 Y:2020 | 07 | 2020 | INSTALL AUTOMATIC PACKING EQUIPMENT | $57,969 | $120,000 | Implemented |
UF0560 # 08 Y:2020 | 08 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $9,639 | $725 | Implemented |
UF0559 # 08 Y:2020 | 08 | 2020 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $5,262 | $7,180 | Implemented |
UF0558 # 03 Y:2020 | 03 | 2020 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $42,983 | $7,127 | Implemented |
UF0555 # 05 Y:2020 | 05 | 2020 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $340,000 | $5,859 | Implemented |
UA0234 # 01 Y:2020 | 01 | 2020 | MODIFY STARTUP/SHUTDOWN TIMES | $17,505 | $0 | Implemented |
IP0141 # 04 Y:2020 | 04 | 2020 | APPLY FOR INVESTMENT INCENTIVES | $2,218 | $2,000 | Implemented |
IP0141 # 03 Y:2020 | 03 | 2020 | APPLY FOR INVESTMENT INCENTIVES | $15,156 | $10,000 | Implemented |
CL2011 # 04 Y:2020 | 04 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $7,830 | $4,500 | Implemented |
CL2010 # 04 Y:2020 | 04 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $14,466 | $4,500 | Implemented |
UF0554 # 05 Y:2020 | 05 | 2020 | INSTALL SENSORS TO DETECT DEFECTS | $3,851 | $15,420 | Implemented |
UF0554 # 04 Y:2020 | 04 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $9,363 | $0 | Implemented |
UF0553 # 05 Y:2020 | 05 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $2,236 | $0 | Implemented |
UF0552 # 01 Y:2020 | 01 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $23,402 | $0 | Implemented |
UF0552 # 06 Y:2020 | 06 | 2020 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $45,577 | $65,793 | Implemented |
WV0596 # 01 Y:2020 | 01 | 2020 | ELIMINATE SHUTDOWNS OF CONTROLS DUE TO OVERHEATING | $103,798 | $40,718 | Implemented |
IC0241 # 03 Y:2020 | 03 | 2020 | PAY BILLS ON TIME TO AVOID LATE FEES | $5,410 | $0 | Implemented |
UU0166 # 01 Y:2020 | 01 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $18,960 | $212,180 | Implemented |
TT0236 # 02 Y:2020 | 02 | 2020 | ADOPT IN-HOUSE MATERIAL GENERATION | $28,629 | $16,000 | Implemented |
UF0550 # 05 Y:2020 | 05 | 2020 | MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE | $383,788 | $897,972 | Implemented |
UU0163 # 07 Y:2020 | 07 | 2020 | ADOPT IN-HOUSE MATERIAL GENERATION | $10,477 | $5,000 | Implemented |
UU0163 # 03 Y:2020 | 03 | 2020 | ADOPT IN-HOUSE MATERIAL GENERATION | $11,324 | $5,000 | Implemented |
UF0548 # 04 Y:2020 | 04 | 2020 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $493,101 | $1,875,550 | Implemented |
NL0046 # 05 Y:2020 | 05 | 2020 | CONDENSE OPERATION INTO ONE BUILDING | $2,848 | $9,480 | Implemented |
UF0544 # 07 Y:2020 | 07 | 2020 | AUTOMATE FINISHING PROCESS | $70,421 | $37,386 | Implemented |