IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

29

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0748 # 05 Y:2003 05 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,272 $17,760 n/a
GT0748 # 04 Y:2003 04 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,314 $2,844 n/a
GT0748 # 03 Y:2003 03 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $28,809 $0 n/a
GT0748 # 02 Y:2003 02 2003 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $44,604 $85,000 n/a
GT0748 # 01 Y:2003 01 2003 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $116,954 $2,000 n/a
GT0748 # 08 Y:2003 08 2003 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $810,975 $4,250,000 n/a
GT0748 # 07 Y:2003 07 2003 UTILIZE A LESS EXPENSIVE COOLING METHOD $22,400 $22,800 n/a
GT0748 # 06 Y:2003 06 2003 USE OPTIMUM TEMPERATURE $76,382 $16,640 n/a
GT0724 # 06 Y:2001 06 2001 USE OPTIMUM TEMPERATURE $45,009 $3,850 Not Implemented
GT0724 # 05 Y:2001 05 2001 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $6,956 $7,500 Implemented
GT0724 # 04 Y:2001 04 2001 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,279 $5,900 Implemented
GT0724 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,832 $1,800 Implemented
GT0724 # 02 Y:2001 02 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,554 $0 Not Implemented
GT0724 # 01 Y:2001 01 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,810 $8,370 n/a
GT0723 # 05 Y:2001 05 2001 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $76,655 $0 Implemented
GT0723 # 06 Y:2001 06 2001 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,965 $1,418 Implemented
GT0723 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,036 $350 Implemented
GT0723 # 03 Y:2001 03 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,660 $825 Implemented
GT0723 # 02 Y:2001 02 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,140 $68,913 Implemented
GT0723 # 01 Y:2001 01 2001 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY $21,103 $60,000 Implemented
GT0403 # 01 Y:1990 01 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $921 $277 Implemented
GT0403 # 06 Y:1990 06 1990 REPAIR AND ELIMINATE STEAM LEAKS $5,760 $275 Implemented
GT0403 # 05 Y:1990 05 1990 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $5,610 $9,150 Not Implemented
GT0403 # 04 Y:1990 04 1990 KEEP BOILER TUBES CLEAN $1,160 $1,000 Implemented
GT0403 # 03 Y:1990 03 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,588 $4,065 Implemented