Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
349
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2311 # 02 Y:2023 | 02 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,795 | $560 | Implemented |
LS2311 # 03 Y:2023 | 03 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,096 | $3,700 | Implemented |
LS2311 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,014 | $39,200 | Implemented |
LS2311 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,616 | $25 | Implemented |
LS2310 # 06 Y:2023 | 06 | 2023 | INCREASE USE OF AUTOMATION | $22,704 | $21,000 | Implemented |
LS2310 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,110 | $3,822 | Implemented |
LS2310 # 08 Y:2023 | 08 | 2023 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $14,536 | $104,400 | Implemented |
LS2310 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $369 | $45 | Implemented |
LS2309 # 02 Y:2023 | 02 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $8,938 | $225 | Implemented |
LS2309 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,886 | $0 | Implemented |
LS2309 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $642 | $521 | Implemented |
LS2309 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,547 | $180 | Implemented |
LS2308 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $878 | $525 | Implemented |
LS1223 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $346 | $100 | Implemented |
LS1223 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,128 | $17,331 | Implemented |
LS1223 # 02 Y:2023 | 02 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $14,390 | $1,190 | Implemented |
LS1223 # 01 Y:2023 | 01 | 2023 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $803 | $0 | Implemented |
LS1123 # 05 Y:2023 | 05 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $2,321 | $2,881 | Implemented |
LS1123 # 02 Y:2023 | 02 | 2023 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,809 | $300 | Implemented |
LS1123 # 01 Y:2023 | 01 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $2,082 | $150 | Implemented |
LS1123 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,349 | $1,730 | Implemented |
LS1123 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $79 | $75 | Implemented |
LS1023 # 01 Y:2023 | 01 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $2,934 | $300 | Implemented |
LS1023 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $763 | $500 | Implemented |
LS1023 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,524 | $3,046 | Implemented |