IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

149

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD1051 # 04 Y:2023 04 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $703 $0 Implemented
UD1051 # 06 Y:2023 06 2023 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $18,807 $0 Implemented
UD1051 # 03 Y:2023 03 2023 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,083 $0 Implemented
UD1051 # 02 Y:2023 02 2023 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,689 $325 Implemented
UD1051 # 01 Y:2023 01 2023 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $6,461 $0 Implemented
UD0888 # 14 Y:2013 14 2013 DEVELOP A REPAIR/REPLACE POLICY $3,770 $0 Implemented
UD0888 # 01 Y:2013 01 2013 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $396 $5,000 Implemented
UD0888 # 07 Y:2013 07 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $7,011 $0 Implemented
UD0888 # 21 Y:2013 21 2013 CONVERT FROM BATCH OPERATION TO CONTINUOUS PROCESSING $4,400 $0 Implemented
UD0888 # 04 Y:2013 04 2013 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,510 $5,000 Implemented
UD0888 # 11 Y:2013 11 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,284 $15,000 Implemented
UD0888 # 20 Y:2013 20 2013 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $412 $0 Implemented
UD0888 # 12 Y:2013 12 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $20,092 $0 Implemented
UD0888 # 09 Y:2013 09 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,246 $3,000 Implemented
UD0888 # 08 Y:2013 08 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,313 $0 Implemented
UD0888 # 02 Y:2013 02 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $841 $0 Implemented
UD0884 # 01 Y:2013 01 2013 OPTIMIZE PLANT POWER FACTOR $9,148 $1,000 Implemented
UD0884 # 08 Y:2013 08 2013 UTILIZE A LESS EXPENSIVE COOLING METHOD $8,876 $0 Implemented
UD0884 # 05 Y:2013 05 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $936 $500 Implemented
UD0884 # 09 Y:2013 09 2013 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $2,533 $2,000 Implemented
UD0884 # 03 Y:2013 03 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,136 $7,000 Implemented
UD0884 # 04 Y:2013 04 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $11,400 $19,000 Implemented
UD0884 # 12 Y:2013 12 2013 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $1,101 $0 Implemented
UD0884 # 11 Y:2013 11 2013 AVOID FROST FORMATION ON EVAPORATORS $1,417 $0 Implemented
UD0884 # 02 Y:2013 02 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,605 $19,350 Implemented