IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,500

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UC2401 # 04 Y:2024 04 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $935 $150 n/a
UC2401 # 09 Y:2024 09 2024 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $719 $1,986 n/a
UC2401 # 02 Y:2024 02 2024 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $8,715 $0 n/a
UC2401 # 07 Y:2024 07 2024 INSTALL TIMERS AND/OR THERMOSTATS $1,271 $653 n/a
UC2401 # 03 Y:2024 03 2024 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $8,586 $48,007 n/a
UC2401 # 05 Y:2024 05 2024 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $612 $1,300 n/a
UC2401 # 06 Y:2024 06 2024 USE SOLAR HEAT TO MAKE ELECTRICTY $26,744 $134,289 n/a
UC2401 # 08 Y:2024 08 2024 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $614 $2,242 n/a
UC2401 # 01 Y:2024 01 2024 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $6,791 $0 n/a
UC2317 # 02 Y:2023 02 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $392 $75 n/a
UC2317 # 09 Y:2023 09 2023 ADOPT IN-HOUSE MATERIAL GENERATION $30,659 $188,853 n/a
UC2317 # 07 Y:2023 07 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,763 $17,190 n/a
UC2317 # 08 Y:2023 08 2023 RECOVER WASTE HEAT FROM EQUIPMENT $1,409 $34,609 n/a
UC2317 # 12 Y:2023 12 2023 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $5,411 $0 n/a
UC2317 # 06 Y:2023 06 2023 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS $714 $540 n/a
UC2317 # 05 Y:2023 05 2023 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $5,240 $50 n/a
UC2317 # 03 Y:2023 03 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,123 $428 n/a
UC2317 # 10 Y:2023 10 2023 INSTALL TIMERS AND/OR THERMOSTATS $6,903 $1,468 n/a
UC2317 # 11 Y:2023 11 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $321,413 $2,701,940 n/a
UC2317 # 01 Y:2023 01 2023 OPTIMIZE PLANT POWER FACTOR $90,350 $29,189 n/a
UC2317 # 04 Y:2023 04 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,584 $1,300 n/a
UC2316 # 05 Y:2023 05 2023 REDUCE EXCESSIVE BOILER BLOWDOWN $2,801 $12,000 n/a
UC2316 # 06 Y:2023 06 2023 BURN A LESS EXPENSIVE GRADE OF FUEL $153,910 $207,578 n/a
UC2316 # 09 Y:2023 09 2023 INSTALL WIND POWERED ELECTRIC GENERATOR $1,380,736 $10,992,131 n/a
UC2316 # 10 Y:2023 10 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $20,195 $268,543 n/a