IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

467

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0205 # 01 Y:2000 01 2000 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $2,248 $0 Implemented
SF0205 # 07 Y:2000 07 2000 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $568 $750 Implemented
SF0205 # 11 Y:2000 11 2000 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $48,746 $120,000 Not Implemented
SF0205 # 05 Y:2000 05 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $8,404 $9,230 Implemented
SF0205 # 02 Y:2000 02 2000 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,267 $781 Implemented
SF0205 # 08 Y:2000 08 2000 INSTALL OCCUPANCY SENSORS $4,509 $7,290 Implemented
SF0205 # 03 Y:2000 03 2000 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,398 $1,128 Implemented
SF0205 # 06 Y:2000 06 2000 INSTALL OCCUPANCY SENSORS $1,007 $1,080 Implemented
SF0205 # 04 Y:2000 04 2000 INSULATE BARE EQUIPMENT $4,536 $4,508 Implemented
SF0205 # 09 Y:2000 09 2000 INSTALL SKYLIGHTS $8,242 $23,962 Not Implemented
SF0205 # 10 Y:2000 10 2000 OPTIMIZE PLANT POWER FACTOR $3,666 $5,428 Not Implemented
OR0383 # 04 Y:2000 04 2000 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $38,785 $45,275 Implemented
OR0383 # 07 Y:2000 07 2000 OPTIMIZE PLANT POWER FACTOR $4,282 $11,900 Not Implemented
OR0383 # 01 Y:2000 01 2000 $121,300 $252,800 Not Implemented
OR0383 # 06 Y:2000 06 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $16,870 $18,000 Implemented
OR0383 # 05 Y:2000 05 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $26,070 $28,457 Implemented
OR0383 # 02 Y:2000 02 2000 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS $114,832 $600 Implemented
OR0383 # 03 Y:2000 03 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $43,523 $3,525 Implemented
SF0204 # 07 Y:2000 07 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $714 $3,660 n/a
SF0204 # 06 Y:2000 06 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,518 $13,006 n/a
SF0204 # 08 Y:2000 08 2000 REUSE / RECYCLE/ SELL PAPER PRODUCTS $615 $46 n/a
SF0204 # 03 Y:2000 03 2000 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $1,179 $2,230 n/a
SF0204 # 05 Y:2000 05 2000 INSTALL OCCUPANCY SENSORS $891 $1,920 n/a
SF0204 # 01 Y:2000 01 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $412 $0 n/a
SF0204 # 04 Y:2000 04 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,335 $3,274 n/a