Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
81
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0439 # 07 Y:2013 | 07 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $400 | $20 | Implemented |
BD0439 # 08 Y:2013 | 08 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $341 | $350 | Implemented |
BD0439 # 03 Y:2013 | 03 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,900 | $1,000 | Implemented |
BD0439 # 01 Y:2013 | 01 | 2013 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $6,296 | $50 | Implemented |
BD0439 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $813 | $795 | Implemented |
BD0438 # 08 Y:2013 | 08 | 2013 | REDUCE EXCESSIVE BOILER BLOWDOWN | $19,230 | $25,000 | Implemented |
BD0438 # 10 Y:2013 | 10 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,975 | $34,500 | Implemented |
BD0438 # 07 Y:2013 | 07 | 2013 | REPAIR OR REPLACE STEAM TRAPS | $42,432 | $1,600 | Implemented |
BD0438 # 05 Y:2013 | 05 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $47,432 | $30 | Implemented |
BD0438 # 04 Y:2013 | 04 | 2013 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $52,832 | $150,000 | Implemented |
BD0438 # 03 Y:2013 | 03 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $63,332 | $57,300 | Implemented |
BD0438 # 01 Y:2013 | 01 | 2013 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $257,500 | $315,000 | Implemented |
BD0438 # 15 Y:2013 | 15 | 2013 | INSTALL / REPAIR INSULATION ON STEAM LINES | $286 | $325 | Implemented |
BD0438 # 16 Y:2013 | 16 | 2013 | INSTALL OCCUPANCY SENSORS | $159 | $32 | Implemented |
BD0438 # 06 Y:2013 | 06 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $46,324 | $10,000 | Implemented |
BD0438 # 14 Y:2013 | 14 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $674 | $550 | Implemented |
BD0438 # 09 Y:2013 | 09 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $27,466 | $20,000 | Implemented |
BD0438 # 12 Y:2013 | 12 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,591 | $25 | Implemented |
BD0438 # 13 Y:2013 | 13 | 2013 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $10,546 | $30,000 | Implemented |
BD0436 # 02 Y:2013 | 02 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $2,974 | $1,500 | Implemented |
BD0434 # 01 Y:2013 | 01 | 2013 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $48,621 | $13,862 | Implemented |
BD0434 # 02 Y:2013 | 02 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,169 | $11,159 | Implemented |
BD0434 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,463 | $1,425 | Implemented |
BD0434 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $1,272 | $1,475 | Implemented |
BD0433 # 08 Y:2013 | 08 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,387 | $20 | Implemented |