IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

46

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0421 # 05 Y:1998 05 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,035 $9,615 Not Implemented
MA0421 # 02 Y:1998 02 1998 BURN A LESS EXPENSIVE GRADE OF FUEL $77,003 $200,000 Not Implemented
MA0421 # 01 Y:1998 01 1998 BURN A LESS EXPENSIVE GRADE OF FUEL $471,027 $984,000 Not Implemented
MA0421 # 08 Y:1998 08 1998 DIRECT WARMEST AIR TO COMBUSTION INTAKE $268 $472 Not Implemented
MA0421 # 06 Y:1998 06 1998 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,867 $0 Not Implemented
MA0421 # 04 Y:1998 04 1998 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $20,501 $22,284 Not Implemented
MA0421 # 03 Y:1998 03 1998 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $28,397 $5,000 Not Implemented
MA0421 # 07 Y:1998 07 1998 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $917 $8,530 Not Implemented
MA0427 # 05 Y:1998 05 1998 CONTRACT A WOOD PALLET RECYCLING COMPANY $3,533 $2,700 Not Implemented
MA0427 # 08 Y:1998 08 1998 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $836 $200 Implemented
MA0427 # 07 Y:1998 07 1998 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,159 $1,840 Not Implemented
MA0427 # 06 Y:1998 06 1998 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $2,828 $426 Implemented
MA0427 # 04 Y:1998 04 1998 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $4,093 $4,800 Not Implemented
MA0427 # 03 Y:1998 03 1998 RECOVER WASTE HEAT FROM EQUIPMENT $2,885 $242 Not Implemented
MA0427 # 02 Y:1998 02 1998 OPTIMIZE PLANT POWER FACTOR $5,715 $7,055 Implemented
MA0427 # 01 Y:1998 01 1998 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $9,186 $19,050 Implemented
MA0424 # 06 Y:1998 06 1998 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,474 $5,800 Not Implemented
MA0424 # 02 Y:1998 02 1998 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $16,538 $30,400 Implemented
MA0424 # 05 Y:1998 05 1998 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $1,568 $0 Implemented
MA0424 # 04 Y:1998 04 1998 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $12,411 $10,638 Not Implemented
MA0424 # 01 Y:1998 01 1998 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $263,073 $1,000,000 Not Implemented
MA0424 # 03 Y:1998 03 1998 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $20,197 $21,808 Not Implemented
MA0419 # 05 Y:1998 05 1998 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $3,822 $9,000 Implemented
MA0419 # 06 Y:1998 06 1998 $3,967 $0 Implemented
MA0419 # 07 Y:1998 07 1998 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,739 $0 Implemented