IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

34

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0498 # 04 Y:2001 04 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,980 $0 Implemented
MA0498 # 02 Y:2001 02 2001 TURN OFF EQUIPMENT WHEN NOT IN USE $10,867 $0 Implemented
MA0498 # 01 Y:2001 01 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $35,844 $60,000 Implemented
MA0498 # 05 Y:2001 05 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $3,300 $13,000 Implemented
MA0498 # 06 Y:2001 06 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,132 $25,540 Implemented
MA0498 # 08 Y:2001 08 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $228 $45 Implemented
MA0493 # 05 Y:2001 05 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $516 $1,000 Implemented
MA0493 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,613 $150 Implemented
MA0493 # 02 Y:2001 02 2001 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $2,846 $0 Implemented
MA0493 # 07 Y:2001 07 2001 $350 $0 Implemented
MA0493 # 06 Y:2001 06 2001 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $161 $100 Implemented
MA0492 # 05 Y:2001 05 2001 INSTALL OCCUPANCY SENSORS $480 $200 Implemented
MA0492 # 02 Y:2001 02 2001 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $5,800 $360 Implemented
MA0486 # 04 Y:2001 04 2001 $3,300 $0 Implemented
MA0486 # 08 Y:2001 08 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $800 $1,100 Implemented
MA0486 # 07 Y:2001 07 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $900 $350 Implemented
MA0486 # 05 Y:2001 05 2001 RECOVER WASTE HEAT FROM EQUIPMENT $1,700 $5,000 Implemented
MA0486 # 02 Y:2001 02 2001 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $10,500 $800 Implemented
MA0483 # 07 Y:2001 07 2001 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $570 $2,500 Implemented
MA0483 # 05 Y:2001 05 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,650 $800 Implemented
MA0483 # 01 Y:2001 01 2001 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $8,700 $0 Implemented
MA0485 # 08 Y:2001 08 2001 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,000 $0 Implemented
MA0485 # 07 Y:2001 07 2001 INSULATE BARE EQUIPMENT $2,300 $10,000 Implemented
MA0485 # 06 Y:2001 06 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,800 $0 Implemented
MA0485 # 05 Y:2001 05 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,100 $10,000 Implemented