IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,673

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DS0003 # 13 Y:1994 13 1994 INCREASE AMOUNT OF CONDENSATE RETURNED $22,360 $4,000 Not Implemented
IA0079 # 01 Y:1994 01 1994 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $18,038 $39,492 Not Implemented
IA0079 # 02 Y:1994 02 1994 INSTALL OCCUPANCY SENSORS $1,520 $2,683 Not Implemented
IA0079 # 03 Y:1994 03 1994 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $239 $537 Not Implemented
IA0079 # 04 Y:1994 04 1994 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,195 $136 Implemented
IA0079 # 05 Y:1994 05 1994 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $852 $45 Implemented
IA0079 # 06 Y:1994 06 1994 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $4,281 $4,200 Not Implemented
IA0061 # 01 Y:1993 01 1993 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $136,096 $379,828 Not Implemented
IA0061 # 02 Y:1993 02 1993 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $68,521 $75,677 Not Implemented
IA0061 # 03 Y:1993 03 1993 REPLACE BOILER $15,800 $23,150 Not Implemented
IA0061 # 04 Y:1993 04 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,928 $1,939 Implemented
IA0061 # 05 Y:1993 05 1993 INSULATE BARE EQUIPMENT $3,751 $3,660 Not Implemented
IA0061 # 06 Y:1993 06 1993 DIRECT WARMEST AIR TO COMBUSTION INTAKE $220 $353 Not Implemented
IA0061 # 07 Y:1993 07 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $110 $120 Implemented
IA0059 # 01 Y:1993 01 1993 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,092 $300 Implemented
IA0059 # 02 Y:1993 02 1993 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,455 $0 Implemented
IA0059 # 03 Y:1993 03 1993 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $8,568 $27,000 Implemented
IA0059 # 04 Y:1993 04 1993 USE DEMAND CONTROLLER OR LOAD SHEDDER $8,390 $5,850 Implemented
IA0059 # 05 Y:1993 05 1993 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $264 $0 Implemented
IA0059 # 06 Y:1993 06 1993 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING $8,376 $1,543 Not Implemented
IA0059 # 07 Y:1993 07 1993 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,828 $1,740 Implemented
IA0059 # 08 Y:1993 08 1993 INSTALL OCCUPANCY SENSORS $1,072 $1,530 Implemented
IA0059 # 09 Y:1993 09 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $978 $120 Implemented
IA0057 # 01 Y:1993 01 1993 TURN OFF EQUIPMENT WHEN NOT IN USE $3,530 $433 Implemented
IA0057 # 02 Y:1993 02 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,451 $2,374 Implemented