IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

14

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0123 # 01 Y:2001 01 2001 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $23,468 $2,500 Implemented
LE0123 # 03 Y:2001 03 2001 INSULATE BARE EQUIPMENT $57,598 $6,000 Implemented
LE0123 # 04 Y:2001 04 2001 CONTRACT A WOOD PALLET RECYCLING COMPANY $13,548 $0 Implemented
LE0104 # 02 Y:2001 02 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $393 $550 Implemented
LE0104 # 04 Y:2001 04 2001 IMPROVE LUBRICATION PRACTICES $378 $400 Implemented
LE0104 # 05 Y:2001 05 2001 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $630 $0 Implemented
LE0102 # 05 Y:2001 05 2001 CONTRACT A WOOD PALLET RECYCLING COMPANY $6,500 $0 Implemented
LE0101 # 01 Y:2001 01 2001 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $9,696 $500 Implemented
LE0101 # 02 Y:2001 02 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS $26,225 $30,000 Implemented
LE0101 # 03 Y:2001 03 2001 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $78,362 $2,500 Implemented
LE0101 # 04 Y:2001 04 2001 IMPROVE LUBRICATION PRACTICES $3,752 $800 Implemented
LE0101 # 05 Y:2001 05 2001 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $89,879 $0 Implemented
LE0101 # 06 Y:2001 06 2001 CLOSE OFF UNNEEDED STEAM LINES $3,984 $2,000 Implemented
LE0101 # 07 Y:2001 07 2001 USE OPTIMUM THICKNESS INSULATION $5,167 $2,000 Implemented