IAC Assessment: AM0060
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0060
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 1989
Principal Product STEEL CASING AND TUBING
NAICS n/a
SIC 3479 - Metal Coating And Allied Services
Sales $5,000,000-$10,000,000
# of Employees 69
Plant Area (Sq.Ft.) 0
Annual Production 6,600 Tons
Production Hrs. Annual 4,144
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $301,358 6,276,671 kWh $0.05
Natural Gas $562,325 178,887 MMBtu $3.14
TOTAL ENERGY COSTS $863,683
RECOMMENDED SAVINGS* $86,170 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $69,580
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER Savings:
$59,200
Cost:
-
- - $59,200 - -
-
kWh
$59,200
-
MMBtu
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$11,080
Cost:
$24,686
$(-870) (-13,482) $11,950 3,807 $(-870)
(-13,482)
kWh
$11,950
3,807
MMBtu
03: 2.2514 COVER OPEN TANKS Savings:
$9,300
Cost:
-
- - $9,300 2,960 -
-
kWh
$9,300
2,960
MMBtu
04: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE Savings:
$2,440
Cost:
$900
$2,440 36,635 - - $2,440
36,635
kWh
-
-
MMBtu
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$1,320
Cost:
-
- - $1,320 420 -
-
kWh
$1,320
420
MMBtu
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$1,210
Cost:
$940
$1,210 38,101 - - $1,210
38,101
kWh
-
-
MMBtu
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$540
Cost:
$420
$540 17,585 - - $540
17,585
kWh
-
-
MMBtu
08: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,080
Cost:
$1,080
- - $1,080 345 -
-
kWh
$1,080
345
MMBtu
TOTAL RECOMMENDED Savings:
$86,170
Cost:
$28,026
$3,320 78,839 $82,850 7,532 $3,320
78,839
kWh
$82,850
7,532
MMBtu
TOTAL IMPLEMENTED Savings:
$69,580
Cost:
$1,080
- - $69,580 3,305 -
-
kWh
$69,580
3,305
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas