Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1989 |
Principal Product | STEEL CASING AND TUBING |
NAICS | n/a |
SIC | 3479 - Metal Coating And Allied Services |
Sales | $5,000,000-$10,000,000 |
# of Employees | 69 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 6,600 Tons |
Production Hrs. Annual | 4,144 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $301,358 | 6,276,671 | kWh | $0.05 |
Natural Gas | $562,325 | 178,887 | MMBtu | $3.14 |
TOTAL ENERGY COSTS | $863,683 | |||
RECOMMENDED SAVINGS* | $86,170 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $69,580 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $59,200 Cost: - |
- | - | $59,200 | - |
- - kWh |
$59,200 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $11,080 Cost: $24,686 |
$(-870) | (-13,482) | $11,950 | 3,807 |
$(-870) (-13,482) kWh |
$11,950 3,807 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2514 COVER OPEN TANKS |
Savings: $9,300 Cost: - |
- | - | $9,300 | 2,960 |
- - kWh |
$9,300 2,960 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $2,440 Cost: $900 |
$2,440 | 36,635 | - | - |
$2,440 36,635 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,320 Cost: - |
- | - | $1,320 | 420 |
- - kWh |
$1,320 420 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,210 Cost: $940 |
$1,210 | 38,101 | - | - |
$1,210 38,101 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $540 Cost: $420 |
$540 | 17,585 | - | - |
$540 17,585 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,080 Cost: $1,080 |
- | - | $1,080 | 345 |
- - kWh |
$1,080 345 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $86,170 Cost: $28,026 |
$3,320 | 78,839 | $82,850 | 7,532 | $3,320 78,839 kWh |
$82,850 7,532 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $69,580 Cost: $1,080 |
- | - | $69,580 | 3,305 | - - kWh |
$69,580 3,305 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |