Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1996 |
Principal Product | Coffee, Tea |
NAICS | n/a |
SIC | 2095 - Roasted Coffee |
Sales | $100,000,000-$500,000,000 |
# of Employees | 234 |
Plant Area (Sq.Ft.) | 250,000 |
Annual Production | 63,000,000 Pounds |
Production Hrs. Annual | 4,277 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $296,850 | 7,765,240 | kWh | $0.04 |
Electricity Demand | $132,380 | 19,507 | kW-months/year | $6.79 |
TOTAL ENERGY COSTS | $475,541 | |||
RECOMMENDED SAVINGS* | $47,880 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $41,770 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $27,300 Cost: $65,100 |
- | - | $27,300 | 2,217 | - | - |
- - kWh |
$27,300 2,217 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,640 Cost: $1,000 |
$2,640 | 131,887 | - | - | - | - |
$2,640 131,887 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $2,040 Cost: $2,500 |
$2,040 | 102,579 | - | - | - | - |
$2,040 102,579 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4155 METER WASTE WATER |
Savings: $9,790 Cost: $2,200 |
- | - | - | - | $9,790 | 20,800,000 |
- - kWh |
- - kW-months/year |
$9,790 20,800,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $6,110 Cost: $4,380 |
- | - | - | - | $6,110 | 8,295,000 |
- - kWh |
- - kW-months/year |
$6,110 8,295,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $47,880 Cost: $75,180 |
$4,680 | 234,466 | $27,300 | 2,217 | $15,900 | 29,095,000 | $4,680 234,466 kWh |
$27,300 2,217 kW-months/year |
$15,900 29,095,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $41,770 Cost: $70,800 |
$4,680 | 234,466 | $27,300 | 2,217 | $9,790 | 20,800,000 | $4,680 234,466 kWh |
$27,300 2,217 kW-months/year |
$9,790 20,800,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal |