Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1997 |
Principal Product | Lithographic printing |
NAICS | n/a |
SIC | 2752 - Commercial Printing, Lithographic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 194 |
Plant Area (Sq.Ft.) | 77,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 6,096 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $113,408 | 2,056,565 | kWh | $0.06 |
Electricity Demand | $18,708 | 6,360 | kW-months/year | $2.94 |
Electricity Fees | $230 | - | $ | - |
TOTAL ENERGY COSTS | $134,066 | |||
RECOMMENDED SAVINGS* | $21,890 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $480 |
#|Description |
Savings Cost |
Status | Electricity Usage | Water Disposal | Solid Waste (non-haz) | Administrative Changes | By-product Production | Electricity Usage | Water Disposal | Solid Waste (non-haz) | Administrative Changes | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | Tgal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $4,800 Cost: $3,900 |
$4,800 | 149,472 | - | - | - | - | - | - | - | - |
$4,800 149,472 kWh |
- - Tgal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $4,570 Cost: - |
- | - | - | - | - | - | - | - | $4,570 | - |
- - kWh |
- - Tgal |
- - lb |
- - $ |
$4,570 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $4,320 Cost: $1,090 |
- | - | - | - | $4,320 | 286,000 | - | - | - | - |
- - kWh |
- - Tgal |
$4,320 286,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,730 Cost: $7,020 |
$2,730 | 74,443 | - | - | - | - | - | - | - | - |
$2,730 74,443 kWh |
- - Tgal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $1,770 Cost: $8,000 |
- | - | - | - | $1,770 | - | - | - | - | - |
- - kWh |
- - Tgal |
$1,770 - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $1,720 Cost: $75 |
- | - | $1,720 | 2,290,000 | - | - | - | - | - | - |
- - kWh |
$1,720 2,290,000 Tgal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $1,500 Cost: - |
- | - | - | - | - | - | $1,500 | - | - | - |
- - kWh |
- - Tgal |
- - lb |
$1,500 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.7198 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT |
Savings: $480 Cost: $110 |
- | - | - | - | $480 | 2,850 | - | - | - | - |
- - kWh |
- - Tgal |
$480 2,850 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $21,890 Cost: $20,195 |
$7,530 | 223,915 | $1,720 | 2,290,000 | $6,570 | 288,850 | $1,500 | - | $4,570 | - | $7,530 223,915 kWh |
$1,720 2,290,000 Tgal |
$6,570 288,850 lb |
$1,500 - $ |
$4,570 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $480 Cost: $110 |
- | - | - | - | $480 | 2,850 | - | - | - | - | - - kWh |
- - Tgal |
$480 2,850 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | Tgal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Water Disposal | Solid Waste (non-haz) | Administrative Changes | By-product Production | Electricity Usage | Water Disposal | Solid Waste (non-haz) | Administrative Changes | By-product Production |