IAC Assessment: AM0349
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0349
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 1999
Principal Product spiral wound and heat exchanger gaskets
NAICS n/a
SIC 3053 - Gaskets, Packing And Sealing Devices
Sales $10,000,000-$50,000,000
# of Employees 180
Plant Area (Sq.Ft.) 52,000
Annual Production 2,000,000 Pieces
Production Hrs. Annual 4,857
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $122,861 1,976,260 kWh $0.06
Electricity Demand $24,573 8,287 kW-months/year $2.97
Electricity Fees $522 - $ -
Natural Gas $13,266 2,506 MMBtu $5.29
TOTAL ENERGY COSTS $171,292
RECOMMENDED SAVINGS* $238,892 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $153,997
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (non-haz) Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Other Liquid (non-haz) Other Liquid (haz) Solid Waste (non-haz) Personnel Changes
$ kWh $ kW-months/year $ gal $ gal $ lb $ $
01: 4.446 AUTOMATE FINISHING PROCESS Savings:
$108,500
Cost:
$30,000
- - - - - - - - - - $108,500 - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
gal
-
-
lb
$108,500
-
$
02: 4.422 UTILIZE OUTSIDE CONTRACTING Savings:
$80,000
Cost:
$160,000
- - - - - - - - - - $80,000 - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
gal
-
-
lb
$80,000
-
$
03: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$13,380
Cost:
$15,600
- - $13,380 2,394 - - - - - - - - -
-
kWh
$13,380
2,394
kW-months/year
-
-
gal
-
-
gal
-
-
lb
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$10,540
Cost:
$1,000
$10,540 202,814 - - - - - - - - - - $10,540
202,814
kWh
-
-
kW-months/year
-
-
gal
-
-
gal
-
-
lb
-
-
$
05: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$12,495
Cost:
$5,500
- - - - - - - - $12,495 97,200 - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
gal
$12,495
97,200
lb
-
-
$
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$7,630
Cost:
-
- - - - - - - - $7,630 22,500 - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
gal
$7,630
22,500
lb
-
-
$
07: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$3,645
Cost:
$590
- - - - $3,645 270 - - - - - - -
-
kWh
-
-
kW-months/year
$3,645
270
gal
-
-
gal
-
-
lb
-
-
$
08: 3.8131 USE WATER-BASED ADHESIVES Savings:
$1,275
Cost:
$1,030
- - - - - - $1,275 101 - - - - -
-
kWh
-
-
kW-months/year
-
-
gal
$1,275
101
gal
-
-
lb
-
-
$
09: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$880
Cost:
$425
$600 11,430 $280 50 - - - - - - - - $600
11,430
kWh
$280
50
kW-months/year
-
-
gal
-
-
gal
-
-
lb
-
-
$
10: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$370
Cost:
-
$370 9,965 - - - - - - - - - - $370
9,965
kWh
-
-
kW-months/year
-
-
gal
-
-
gal
-
-
lb
-
-
$
11: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$177
Cost:
-
- - - - - - - - - - $177 - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
gal
-
-
lb
$177
-
$
TOTAL RECOMMENDED Savings:
$238,892
Cost:
$214,145
$11,510 224,209 $13,660 2,444 $3,645 270 $1,275 101 $20,125 119,700 $188,677 - $11,510
224,209
kWh
$13,660
2,444
kW-months/year
$3,645
270
gal
$1,275
101
gal
$20,125
119,700
lb
$188,677
-
$
TOTAL IMPLEMENTED Savings:
$153,997
Cost:
$53,130
$10,540 202,814 $13,380 2,394 - - $1,275 101 $20,125 119,700 $108,677 - $10,540
202,814
kWh
$13,380
2,394
kW-months/year
-
-
gal
$1,275
101
gal
$20,125
119,700
lb
$108,677
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ gal $ lb $ $
Electricity Usage Electricity Demand Other Liquid (non-haz) Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Other Liquid (non-haz) Other Liquid (haz) Solid Waste (non-haz) Personnel Changes