IAC Assessment: AM0373
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0373
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2000
Principal Product Critical service pipe connectors, closures and metal flanges
NAICS n/a
SIC 3494 - Valves And Pipe Fittings, Nec
Sales $10,000,000-$50,000,000
# of Employees 45
Plant Area (Sq.Ft.) 12,000
Annual Production 144,000 Pounds
Production Hrs. Annual 6,600
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $35,365 660,023 kWh $0.05
Electricity Demand $5,158 1,784 kW-months/year $2.89
TOTAL ENERGY COSTS $40,523
RECOMMENDED SAVINGS* $81,450 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $80,150
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes
$ kWh $ kW-months/year $ lb $ $
01: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE Savings:
$75,370
Cost:
-
- - - - $75,370 - - - -
-
kWh
-
-
kW-months/year
$75,370
-
lb
-
-
$
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,650
Cost:
$2,100
- - $1,650 125 - - - - -
-
kWh
$1,650
125
kW-months/year
-
-
lb
-
-
$
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,300
Cost:
$590
$375 14,947 $925 70 - - - - $375
14,947
kWh
$925
70
kW-months/year
-
-
lb
-
-
$
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,070
Cost:
$16
$500 19,930 $570 43 - - - - $500
19,930
kWh
$570
43
kW-months/year
-
-
lb
-
-
$
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$930
Cost:
$200
$930 37,222 - - - - - - $930
37,222
kWh
-
-
kW-months/year
-
-
lb
-
-
$
06: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$710
Cost:
$2,350
$710 28,136 - - - - - - $710
28,136
kWh
-
-
kW-months/year
-
-
lb
-
-
$
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$320
Cost:
-
$110 4,396 $210 16 - - - - $110
4,396
kWh
$210
16
kW-months/year
-
-
lb
-
-
$
08: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$100
Cost:
-
- - - - - - $100 - -
-
kWh
-
-
kW-months/year
-
-
lb
$100
-
$
TOTAL RECOMMENDED Savings:
$81,450
Cost:
$5,256
$2,625 104,631 $3,355 254 $75,370 - $100 - $2,625
104,631
kWh
$3,355
254
kW-months/year
$75,370
-
lb
$100
-
$
TOTAL IMPLEMENTED Savings:
$80,150
Cost:
$4,666
$2,250 89,684 $2,430 184 $75,370 - $100 - $2,250
89,684
kWh
$2,430
184
kW-months/year
$75,370
-
lb
$100
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes