IAC Assessment: AM0389
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0389
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2001
Principal Product Steel drums
NAICS n/a
SIC 3412 - Metal Barrels, Drums, And Pails
Sales $10,000,000-$50,000,000
# of Employees 130
Plant Area (Sq.Ft.) 109,000
Annual Production 1,800,000 Pieces
Production Hrs. Annual 2,875
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $349,083 5,047,215 kWh $0.07
Electricity Demand $111,637 17,746 kW-months/year $6.29
Natural Gas $181,713 52,642 MMBtu $3.45
TOTAL ENERGY COSTS $642,433
RECOMMENDED SAVINGS* $190,240 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $85,180
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $ $ $
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$97,950
Cost:
$233,444
- - - - $32,450 5,500 - - $65,500 - - - - - -
-
kWh
-
-
kW-months/year
$32,450
5,500
MMBtu
-
-
lb
$65,500
-
$
-
-
$
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$51,000
Cost:
$2,500
$51,000 1,040,000 - - - - - - - - - - - - $51,000
1,040,000
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
03: 3.2176 INCREASE USE OF AUTOMATION Savings:
$24,140
Cost:
$57,000
$(-270) (-5,500) $(-340) (-40) - - - - - - - - $24,750 - $(-270)
(-5,500)
kWh
$(-340)
(-40)
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
$24,750
-
$
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$7,000
Cost:
$18,250
- - $7,000 811 - - - - - - - - - - -
-
kWh
$7,000
811
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
05: 3.1162 USE LESS WASTEFUL PACKAGING Savings:
$5,000
Cost:
$4,442
- - - - - - $5,000 - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$5,000
-
lb
-
-
$
-
-
$
-
-
$
06: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$5,040
Cost:
-
- - - - - - - - - - $5,040 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
$5,040
-
$
-
-
$
07: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$110
Cost:
-
$60 1,300 $50 6 - - - - - - - - - - $60
1,300
kWh
$50
6
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$190,240
Cost:
$315,636
$50,790 1,035,800 $6,710 777 $32,450 5,500 $5,000 - $65,500 - $5,040 - $24,750 - $50,790
1,035,800
kWh
$6,710
777
kW-months/year
$32,450
5,500
MMBtu
$5,000
-
lb
$65,500
-
$
$5,040
-
$
$24,750
-
$
TOTAL IMPLEMENTED Savings:
$85,180
Cost:
$63,942
$50,730 1,034,500 $(-340) (-40) - - $5,000 - - - $5,040 - $24,750 - $50,730
1,034,500
kWh
$(-340)
(-40)
kW-months/year
-
-
MMBtu
$5,000
-
lb
-
-
$
$5,040
-
$
$24,750
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product