Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2001 |
Principal Product | Steel drums |
NAICS | n/a |
SIC | 3412 - Metal Barrels, Drums, And Pails |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 109,000 |
Annual Production | 1,800,000 Pieces |
Production Hrs. Annual | 2,875 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $349,083 | 5,047,215 | kWh | $0.07 |
Electricity Demand | $111,637 | 17,746 | kW-months/year | $6.29 |
Natural Gas | $181,713 | 52,642 | MMBtu | $3.45 |
TOTAL ENERGY COSTS | $642,433 | |||
RECOMMENDED SAVINGS* | $190,240 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $85,180 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $97,950 Cost: $233,444 |
- | - | - | - | $32,450 | 5,500 | - | - | $65,500 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$32,450 5,500 MMBtu |
- - lb |
$65,500 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $51,000 Cost: $2,500 |
$51,000 | 1,040,000 | - | - | - | - | - | - | - | - | - | - | - | - |
$51,000 1,040,000 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.2176 INCREASE USE OF AUTOMATION |
Savings: $24,140 Cost: $57,000 |
$(-270) | (-5,500) | $(-340) | (-40) | - | - | - | - | - | - | - | - | $24,750 | - |
$(-270) (-5,500) kWh |
$(-340) (-40) kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
$24,750 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $7,000 Cost: $18,250 |
- | - | $7,000 | 811 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$7,000 811 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.1162 USE LESS WASTEFUL PACKAGING |
Savings: $5,000 Cost: $4,442 |
- | - | - | - | - | - | $5,000 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$5,000 - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $5,040 Cost: - |
- | - | - | - | - | - | - | - | - | - | $5,040 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$5,040 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $110 Cost: - |
$60 | 1,300 | $50 | 6 | - | - | - | - | - | - | - | - | - | - |
$60 1,300 kWh |
$50 6 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $190,240 Cost: $315,636 |
$50,790 | 1,035,800 | $6,710 | 777 | $32,450 | 5,500 | $5,000 | - | $65,500 | - | $5,040 | - | $24,750 | - | $50,790 1,035,800 kWh |
$6,710 777 kW-months/year |
$32,450 5,500 MMBtu |
$5,000 - lb |
$65,500 - $ |
$5,040 - $ |
$24,750 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $85,180 Cost: $63,942 |
$50,730 | 1,034,500 | $(-340) | (-40) | - | - | $5,000 | - | - | - | $5,040 | - | $24,750 | - | $50,730 1,034,500 kWh |
$(-340) (-40) kW-months/year |
- - MMBtu |
$5,000 - lb |
- - $ |
$5,040 - $ |
$24,750 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Product |