IAC Assessment: AM0414
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0414
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2002
Principal Product Aluminum or steel truck trailers
NAICS n/a
SIC 3715 - Truck Trailers
Sales $10,000,000-$50,000,000
# of Employees 90
Plant Area (Sq.Ft.) 66,250
Annual Production 450 Pieces
Production Hrs. Annual 2,142
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $98,166 838,040 kWh $0.12
Electricity Demand $17,574 6,269 kW-months/year $2.80
TOTAL ENERGY COSTS $115,740
RECOMMENDED SAVINGS* $10,519 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,234
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Personnel Changes Electricity Usage Electricity Demand Water Disposal Personnel Changes
$ kWh $ kW-months/year $ Tgal $ $
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$3,400
Cost:
$6,400
- - $3,400 840 - - - - -
-
kWh
$3,400
840
kW-months/year
-
-
Tgal
-
-
$
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$1,815
Cost:
$100
$1,815 22,300 - - - - - - $1,815
22,300
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
03: 3.7132 REUSE RAGS UNTIL COMPLETELY SOILED Savings:
$1,800
Cost:
-
- - - - $1,800 1,500 - - -
-
kWh
-
-
kW-months/year
$1,800
1,500
Tgal
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$795
Cost:
$200
$795 11,260 - - - - - - $795
11,260
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$485
Cost:
-
$485 5,575 - - - - - - $485
5,575
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$480
Cost:
$200
$480 6,850 - - - - - - $480
6,850
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$530
Cost:
$200
$530 6,680 - - - - - - $530
6,680
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
08: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$400
Cost:
$550
$400 5,660 - - - - - - $400
5,660
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
09: 4.8210 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$229
Cost:
-
- - - - - - $229 - -
-
kWh
-
-
kW-months/year
-
-
Tgal
$229
-
$
10: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$240
Cost:
-
$240 3,400 - - - - - - $240
3,400
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
11: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$175
Cost:
$100
$175 2,000 - - - - - - $175
2,000
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
12: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$170
Cost:
$50
$170 1,890 - - - - - - $170
1,890
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
TOTAL RECOMMENDED Savings:
$10,519
Cost:
$7,800
$5,090 65,615 $3,400 840 $1,800 1,500 $229 - $5,090
65,615
kWh
$3,400
840
kW-months/year
$1,800
1,500
Tgal
$229
-
$
TOTAL IMPLEMENTED Savings:
$6,234
Cost:
$850
$4,205 54,380 - - $1,800 1,500 $229 - $4,205
54,380
kWh
-
-
kW-months/year
$1,800
1,500
Tgal
$229
-
$
Savings
Cost
$ kWh $ kW-months/year $ Tgal $ $
Electricity Usage Electricity Demand Water Disposal Personnel Changes Electricity Usage Electricity Demand Water Disposal Personnel Changes