Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2006 |
Principal Product | Metal stampings |
NAICS | 332119 - Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
SIC | 3469 - Metal Stampings, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 25,000,000 Pieces |
Production Hrs. Annual | 4,700 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $106,484 | 3,167,520 | kWh | $0.03 |
Electricity Demand | $77,039 | 8,958 | kW-months/year | $8.60 |
Electricity Fees | $2,400 | - | $ | - |
TOTAL ENERGY COSTS | $185,923 | |||
RECOMMENDED SAVINGS* | $22,281 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $17,000 Cost: $1,000 |
$15,200 | 220,000 | $1,800 | 560 | - | - | - | - |
$15,200 220,000 kWh |
$1,800 560 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $2,400 Cost: $7,650 |
- | - | - | - | - | - | $2,400 | - |
- - kWh |
- - kW-months/year |
- - lb |
$2,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $1,155 Cost: - |
$1,034 | 14,988 | $121 | 38 | - | - | - | - |
$1,034 14,988 kWh |
$121 38 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $686 Cost: - |
$620 | 8,960 | $66 | 21 | - | - | - | - |
$620 8,960 kWh |
$66 21 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5217 REUSE / RECYCLE/ SELL PAPER PRODUCTS |
Savings: $455 Cost: - |
- | - | - | - | $455 | 59,000 | - | - |
- - kWh |
- - kW-months/year |
$455 59,000 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $420 Cost: - |
- | - | - | - | $420 | 6,400 | - | - |
- - kWh |
- - kW-months/year |
$420 6,400 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $165 Cost: - |
$165 | 4,000 | - | - | - | - | - | - |
$165 4,000 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,281 Cost: $8,650 |
$17,019 | 247,948 | $1,987 | 619 | $875 | 65,400 | $2,400 | - | $17,019 247,948 kWh |
$1,987 619 kW-months/year |
$875 65,400 lb |
$2,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes |