IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2006 |
Principal Product | Oil field specialty chemicals |
NAICS | 325180 - Other Basic Inorganic Chemical Manufacturing |
SIC | 2819 - Industrial Inorganic Chemicals, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 32,000,000 Pounds |
Production Hrs. Annual | 3,980 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $96,567 | 1,379,400 | kWh | $0.07 |
Electricity Demand | $17,400 | 4,920 | kW-months/year | $3.54 |
Electricity Fees | $55 | - | $ | - |
Natural Gas | $210,351 | 19,917 | MMBtu | $10.56 |
TOTAL ENERGY COSTS | $324,373 | |||
RECOMMENDED SAVINGS* | $74,820 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $74,147 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $7,530 Cost: $500 |
- | - | $7,530 | 700 | - | - | - | - |
- - kWh |
$7,530 700 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $31,494 Cost: $12,000 |
- | - | - | - | $6,294 | - | $25,200 | - |
- - kWh |
- - MMBtu |
$6,294 - $ |
$25,200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $30,123 Cost: $12,050 |
- | - | - | - | $6,023 | - | $24,100 | - |
- - kWh |
- - MMBtu |
$6,023 - $ |
$24,100 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $4,570 Cost: $1,000 |
- | - | $4,570 | 425 | - | - | - | - |
- - kWh |
$4,570 425 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $673 Cost: - |
- | - | - | - | $673 | - | - | - |
- - kWh |
- - MMBtu |
$673 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $430 Cost: - |
$430 | 8,470 | - | - | - | - | - | - |
$430 8,470 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $74,820 Cost: $25,550 |
$430 | 8,470 | $12,100 | 1,125 | $12,990 | - | $49,300 | - | $430 8,470 kWh |
$12,100 1,125 MMBtu |
$12,990 - $ |
$49,300 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $74,147 Cost: $25,550 |
$430 | 8,470 | $12,100 | 1,125 | $12,317 | - | $49,300 | - | $430 8,470 kWh |
$12,100 1,125 MMBtu |
$12,317 - $ |
$49,300 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost |