Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2015 |
Principal Product | Precision machining |
NAICS | 332710 - Machine Shops |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 109 |
Plant Area (Sq.Ft.) | 227,500 |
Annual Production | 21,530 Pieces |
Production Hrs. Annual | 2,490 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $546,031 | 8,941,947 | kWh | $0.06 |
Electricity Demand | $173,415 | 24,909 | kW-months/year | $6.96 |
Electricity Fees | $3,884 | - | $ | - |
TOTAL ENERGY COSTS | $723,330 | |||
RECOMMENDED SAVINGS* | $88,580 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | Ancillary Material Cost | Electricity Usage | Electricity Demand | LPG | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $17,950 Cost: $12,830 |
- | - | - | - | $(-3,650) | (-186) | $21,600 | - |
- - kWh |
- - kW-months/year |
$(-3,650) (-186) MMBtu |
$21,600 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $17,320 Cost: $2,000 |
$9,900 | 170,600 | $7,420 | 1,028 | - | - | - | - |
$9,900 170,600 kWh |
$7,420 1,028 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $14,550 Cost: $31,640 |
- | - | $14,550 | 2,015 | - | - | - | - |
- - kWh |
$14,550 2,015 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $11,210 Cost: $21,860 |
- | - | $11,210 | 1,553 | - | - | - | - |
- - kWh |
$11,210 1,553 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $8,400 Cost: $9,800 |
- | - | - | - | - | - | $8,400 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$8,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $8,190 Cost: $10,960 |
$4,670 | 80,500 | $3,520 | 488 | - | - | - | - |
$4,670 80,500 kWh |
$3,520 488 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $4,570 Cost: $11,330 |
- | - | $4,570 | 633 | - | - | - | - |
- - kWh |
$4,570 633 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $4,060 Cost: $1,270 |
$4,060 | 69,950 | - | - | - | - | - | - |
$4,060 69,950 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,330 Cost: $30 |
$1,330 | 22,965 | $1,000 | 138 | - | - | - | - |
$1,330 22,965 kWh |
$1,000 138 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $88,580 Cost: $101,720 |
$19,960 | 344,015 | $42,270 | 5,855 | $(-3,650) | (-186) | $30,000 | - | $19,960 344,015 kWh |
$42,270 5,855 kW-months/year |
$(-3,650) (-186) MMBtu |
$30,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | Ancillary Material Cost | Electricity Usage | Electricity Demand | LPG | Ancillary Material Cost |