IAC Assessment: AS0108
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0108
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 1994
Principal Product Electroluminescent Lighting
NAICS n/a
SIC 3641 - Electric Lamps
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 22,500
Annual Production 500,000 Pieces
Production Hrs. Annual 8,112
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $120,835 1,791,325 kWh $0.07
TOTAL ENERGY COSTS $120,835
RECOMMENDED SAVINGS* $15,288 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $546
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,756
Cost:
$825
$1,756 26,084 $1,756
26,084
kWh
02: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$2,004
Cost:
$1,342
$2,004 29,894 $2,004
29,894
kWh
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$546
Cost:
$500
$546 8,206 $546
8,206
kWh
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$2,997
Cost:
$585
$2,997 44,549 $2,997
44,549
kWh
05: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$7,611
Cost:
$26,535
$7,611 112,837 $7,611
112,837
kWh
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$374
Cost:
$2,060
$374 5,569 $374
5,569
kWh
TOTAL RECOMMENDED Savings:
$15,288
Cost:
$31,847
$15,288 227,139 $15,288
227,139
kWh
TOTAL IMPLEMENTED Savings:
$546
Cost:
$500
$546 8,206 $546
8,206
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage