IAC Assessment: AS0311
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0311
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2001
Principal Product Commercial printing and packaging
NAICS n/a
SIC 2752 - Commercial Printing, Lithographic
Sales $5,000,000-$10,000,000
# of Employees 30
Plant Area (Sq.Ft.) 47,000
Annual Production 50,000,000 Pieces
Production Hrs. Annual 5,240
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $123,616 1,261,800 kWh $0.10
Electricity Fees $12,044 - $ -
Natural Gas $1,294 125 MMBtu $10.35
TOTAL ENERGY COSTS $136,954
RECOMMENDED SAVINGS* $88,017 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Personnel Changes Administrative Changes Electricity Usage Personnel Changes Administrative Changes
$ kWh $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,056
Cost:
$112
$1,056 9,950 - - - - $1,056
9,950
kWh
-
-
$
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$404
Cost:
$225
$404 3,810 - - - - $404
3,810
kWh
-
-
$
-
-
$
03: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$1,920
Cost:
$60
- - - - $1,920 - -
-
kWh
-
-
$
$1,920
-
$
04: 4.4450 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$40,872
Cost:
$100,000
- - $40,872 - - - -
-
kWh
$40,872
-
$
-
-
$
05: 4.3230 OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS Savings:
$7,765
Cost:
$4,414
- - - - $7,765 - -
-
kWh
-
-
$
$7,765
-
$
06: 4.4310 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$36,000
Cost:
$1,078
- - - - $36,000 - -
-
kWh
-
-
$
$36,000
-
$
TOTAL RECOMMENDED Savings:
$88,017
Cost:
$105,889
$1,460 13,760 $40,872 - $45,685 - $1,460
13,760
kWh
$40,872
-
$
$45,685
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
$
-
-
$
Savings
Cost
$ kWh $ $ $ $
Electricity Usage Personnel Changes Administrative Changes Electricity Usage Personnel Changes Administrative Changes