Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2006 |
Principal Product | Chrome-coated pieces |
NAICS | 336411 - Aircraft Manufacturing |
SIC | 3471 - Plating And Polishing |
Sales | $500,000-$1,000,000 |
# of Employees | 11 |
Plant Area (Sq.Ft.) | 4,080 |
Annual Production | 1,500 Pieces |
Production Hrs. Annual | 2,420 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $39,545 | 403,680 | kWh | $0.10 |
TOTAL ENERGY COSTS | $43,928 | |||
RECOMMENDED SAVINGS* | $83,360 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Other Liquid (haz) | One-time Revenue or Avoided Cost | Electricity Usage | Other Liquid (haz) | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $79,716 Cost: $39,658 |
- | - | - | - | $79,716 | - |
- - kWh |
- - gal |
$79,716 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6112 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME |
Savings: $3,068 Cost: $1,500 |
- | - | $3,068 | 1,848 | - | - |
- - kWh |
$3,068 1,848 gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3312 INSTALL EFFICIENT RECTIFIERS |
Savings: $576 Cost: $15,000 |
$576 | 9,000 | - | - | - | - |
$576 9,000 kWh |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $83,360 Cost: $56,158 |
$576 | 9,000 | $3,068 | 1,848 | $79,716 | - | $576 9,000 kWh |
$3,068 1,848 gal |
$79,716 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Other Liquid (haz) | One-time Revenue or Avoided Cost | Electricity Usage | Other Liquid (haz) | One-time Revenue or Avoided Cost |