Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of North Carolina, Charlotte |
---|---|
Assessment Year | 2022 |
Principal Product | Packaging Tape |
NAICS | 322220 - Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2671 - Paper Coated & Laminated, Packaging |
Sales | $50,000,000-$100,000,000 |
# of Employees | 95 |
Plant Area (Sq.Ft.) | 130,000 |
Annual Production | 412 Units |
Production Hrs. Annual | 8,760 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $312,784 | 8,314,605 | kWh | $0.04 |
Electricity Demand | $162,175 | 15,901 | kW-months/year | $10.20 |
Electricity Fees | $2,624 | - | $ | - |
Natural Gas | $271,398 | 46,558 | MMBtu | $5.83 |
TOTAL ENERGY COSTS | $748,981 | |||
RECOMMENDED SAVINGS* | $54,897 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,092 Cost: $17,800 |
$4,104 | 108,006 | $988 | 97 | - | - |
$4,104 108,006 kWh |
$988 97 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,936 Cost: $4,400 |
$1,530 | 40,253 | $406 | 40 | - | - |
$1,530 40,253 kWh |
$406 40 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $364 Cost: - |
$364 | 9,574 | - | - | - | - |
$364 9,574 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $6,805 Cost: $18,800 |
$4,972 | 130,865 | $1,833 | 180 | - | - |
$4,972 130,865 kWh |
$1,833 180 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,005 Cost: $1,000 |
$2,197 | 57,816 | $808 | 79 | - | - |
$2,197 57,816 kWh |
$808 79 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,056 Cost: $8,000 |
- | - | - | - | $3,056 | 524 |
- - kWh |
- - kW-months/year |
$3,056 524 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $10,680 Cost: $40,000 |
$(-460) | (-12,102) | $(-169) | (-17) | $11,309 | 1,940 |
$(-460) (-12,102) kWh |
$(-169) (-17) kW-months/year |
$11,309 1,940 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2612 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION |
Savings: $15,506 Cost: $58,000 |
$12,310 | 323,944 | $3,196 | 313 | - | - |
$12,310 323,944 kWh |
$3,196 313 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $8,453 Cost: $500 |
- | - | - | - | $8,453 | 1,450 |
- - kWh |
- - kW-months/year |
$8,453 1,450 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $54,897 Cost: $148,500 |
$25,017 | 658,356 | $7,062 | 692 | $22,818 | 3,914 | $25,017 658,356 kWh |
$7,062 692 kW-months/year |
$22,818 3,914 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |