Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2007 |
Principal Product | Prime mover controls |
NAICS | 311999 - All Other Miscellaneous Food Manufacturing |
SIC | 3625 - Relays And Industrial Controls |
Sales | $50,000,000-$100,000,000 |
# of Employees | 1,000 |
Plant Area (Sq.Ft.) | 223,000 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 3,744 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $283,225 | 15,625,400 | kWh | $0.02 |
Electricity Demand | $417,648 | 53,228 | kW-months/year | $7.85 |
Electricity Fees | $384 | - | $ | - |
Natural Gas | $200,926 | 23,908 | MMBtu | $8.40 |
TOTAL ENERGY COSTS | $902,183 | |||
RECOMMENDED SAVINGS* | $43,650 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $43,650 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $11,650 Cost: $56,600 |
$5,190 | 278,300 | $6,460 | 792 | - | - |
$5,190 278,300 kWh |
$6,460 792 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,530 Cost: $1,500 |
$2,060 | 110,500 | $2,470 | 302 | - | - |
$2,060 110,500 kWh |
$2,470 302 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,470 Cost: $60 |
$1,780 | 95,300 | $1,690 | 206 | - | - |
$1,780 95,300 kWh |
$1,690 206 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1224 REPLACE BOILER |
Savings: $23,660 Cost: $20,000 |
$1,890 | 101,300 | $2,230 | 274 | $19,540 | 2,878 |
$1,890 101,300 kWh |
$2,230 274 kW-months/year |
$19,540 2,878 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $340 Cost: $1,370 |
$280 | 14,800 | $60 | 8 | - | - |
$280 14,800 kWh |
$60 8 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $43,650 Cost: $79,530 |
$11,200 | 600,200 | $12,910 | 1,582 | $19,540 | 2,878 | $11,200 600,200 kWh |
$12,910 1,582 kW-months/year |
$19,540 2,878 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $43,650 Cost: $79,530 |
$11,200 | 600,200 | $12,910 | 1,582 | $19,540 | 2,878 | $11,200 600,200 kWh |
$12,910 1,582 kW-months/year |
$19,540 2,878 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |