IAC Assessment: DL0035
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DL0035
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Delaware
Assessment Year 2009
Principal Product Paint Manufacturing
NAICS 325510 - Paint and Coating Manufacturing
SIC 2851 - Paints And Allied Products
Sales $100,000,000-$500,000,000
# of Employees 156
Plant Area (Sq.Ft.) 139,000
Annual Production 29,300 Thousand Gallons
Production Hrs. Annual 6,240
Location (State) MD
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,270,416 13,120,460 kWh $0.10
Natural Gas $1,324,140 1,251,470 MMBtu $1.06
Other Energy $82,587 2,247 MMBtu $36.75
TOTAL ENERGY COSTS $2,708,643
RECOMMENDED SAVINGS* $217,268 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $34,425
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$70,852
Cost:
$10,000
- - $70,852 6,696 -
-
kWh
$70,852
6,696
MMBtu
02: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$76,620
Cost:
$120,000
- - $76,620 7,450 -
-
kWh
$76,620
7,450
MMBtu
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$34,425
Cost:
$12,000
$34,425 405,000 - - $34,425
405,000
kWh
-
-
MMBtu
04: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) Savings:
$28,800
Cost:
$44,500
- - $28,800 2,880 -
-
kWh
$28,800
2,880
MMBtu
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$4,041
Cost:
-
$4,041 37,776 - - $4,041
37,776
kWh
-
-
MMBtu
06: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE Savings:
$2,530
Cost:
-
- - $2,530 252 -
-
kWh
$2,530
252
MMBtu
TOTAL RECOMMENDED Savings:
$217,268
Cost:
$186,500
$38,466 442,776 $178,802 17,278 $38,466
442,776
kWh
$178,802
17,278
MMBtu
TOTAL IMPLEMENTED Savings:
$34,425
Cost:
$12,000
$34,425 405,000 - - $34,425
405,000
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas