Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2012 |
Principal Product | capital equipment fo the corrugated box industry |
NAICS | 333243 - Sawmill, Woodworking, and Paper Machinery Manufacturing |
SIC | 3554 - Paper Industries Machinery |
Sales | $50,000,000-$100,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 2,147,483,647 Units |
Production Hrs. Annual | 7,488 |
Location (State) | MD |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $752,528 | 6,046,950 | kWh | $0.12 |
Natural Gas | $122,814 | 9,681 | MMBtu | $12.69 |
TOTAL ENERGY COSTS | $875,342 | |||
RECOMMENDED SAVINGS* | $161,388 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $93,515 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7262 SEPARATE CONTROLS OF AIR HANDLERS FROM AC/ HEATING SYSTEMS |
Savings: $37,175 Cost: $100 |
$37,175 | 299,800 | - | - |
$37,175 299,800 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $7,948 Cost: $100 |
- | - | $7,948 | 626 |
- - kWh |
$7,948 626 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $9,212 Cost: $6,080 |
- | - | $9,212 | 726 |
- - kWh |
$9,212 726 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $25,500 Cost: $21,080 |
$25,500 | 205,500 | - | - |
$25,500 205,500 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $32,910 Cost: $51,500 |
$32,910 | 265,430 | - | - |
$32,910 265,430 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $7,995 Cost: $4,850 |
- | - | $7,995 | 630 |
- - kWh |
$7,995 630 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,020 Cost: $2,800 |
$4,020 | 32,400 | - | - |
$4,020 32,400 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,640 Cost: $620 |
$2,640 | 21,340 | - | - |
$2,640 21,340 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $23,794 Cost: $80,000 |
- | - | $23,794 | 1,875 |
- - kWh |
$23,794 1,875 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7244 REVISE SMOKE CLEANUP FROM OPERATIONS |
Savings: $3,290 Cost: $11,200 |
$3,290 | 26,500 | - | - |
$3,290 26,500 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $5,894 Cost: $11,040 |
$(-1,860) | (-15,000) | $7,754 | 611 |
$(-1,860) (-15,000) kWh |
$7,754 611 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $1,010 Cost: $500 |
$1,010 | 8,150 | - | - |
$1,010 8,150 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $161,388 Cost: $189,870 |
$104,685 | 844,120 | $56,703 | 4,468 | $104,685 844,120 kWh |
$56,703 4,468 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $93,515 Cost: $98,230 |
$68,360 | 551,170 | $25,155 | 1,982 | $68,360 551,170 kWh |
$25,155 1,982 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |