Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2024 |
Principal Product | components for mammography and other diagnostic equipment |
NAICS | 334510 - Electromedical and Electrotherapeutic Apparatus Manufacturing |
SIC | 3844 - X-ray Apparatus And Tubes |
Sales | $100,000,000-$500,000,000 |
# of Employees | 375 |
Plant Area (Sq.Ft.) | 195,000 |
Annual Production | 1,000 Units |
Production Hrs. Annual | 5,070 |
Location (State) | DE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $487,283 | 6,436,351 | kWh | $0.08 |
Electricity Demand | $70,180 | 11,590 | kW-months/year | $6.06 |
Electricity Fees | $14,939 | - | $ | - |
Natural Gas | $90,322 | 9,149 | MMBtu | $9.87 |
TOTAL ENERGY COSTS | $662,724 | |||
RECOMMENDED SAVINGS* | $41,715 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $30,655 Cost: $117,000 |
$14,626 | 187,515 | $16,029 | 1,624 |
$14,626 187,515 kWh |
$16,029 1,624 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE |
Savings: $7,985 Cost: $4,420 |
$7,985 | 102,374 | - | - |
$7,985 102,374 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,075 Cost: $5,000 |
$3,075 | 39,420 | - | - |
$3,075 39,420 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $41,715 Cost: $126,420 |
$25,686 | 329,309 | $16,029 | 1,624 | $25,686 329,309 kWh |
$16,029 1,624 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |