Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | South Dakota State |
---|---|
Assessment Year | 2000 |
Principal Product | Metal Finishing |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $5,000,000-$10,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 42,000 |
Annual Production | 39,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | MN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $60,253 | 1,685,522 | kWh | $0.04 |
Electricity Demand | $51,407 | 6,876 | kW-months/year | $7.48 |
Electricity Fees | $918 | - | $ | - |
Natural Gas | $96,092 | 21,376 | MMBtu | $4.50 |
LPG | $2,817 | 281 | MMBtu | $10.02 |
TOTAL ENERGY COSTS | $336,882 | |||
RECOMMENDED SAVINGS* | $9,099 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Natural Gas | Water Disposal | Administrative Changes | Natural Gas | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $2,370 Cost: $688 |
$2,370 | 527 | - | - | - | - |
$2,370 527 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $5,432 Cost: $800 |
- | - | $5,432 | 2,361,840 | - | - |
- - MMBtu |
$5,432 2,361,840 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $1,297 Cost: - |
- | - | - | - | $1,297 | - |
- - MMBtu |
- - Tgal |
$1,297 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $9,099 Cost: $1,488 |
$2,370 | 527 | $5,432 | 2,361,840 | $1,297 | - | $2,370 527 MMBtu |
$5,432 2,361,840 Tgal |
$1,297 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Natural Gas | Water Disposal | Administrative Changes | Natural Gas | Water Disposal | Administrative Changes |