Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1999 |
Principal Product | VHS Cassettes |
NAICS | n/a |
SIC | 3695 - Magnetic And Optical Recording Media |
Sales | $50,000,000-$100,000,000 |
# of Employees | 170 |
Plant Area (Sq.Ft.) | 125,000 |
Annual Production | 74,600,000 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $433,461 | 8,044,842 | kWh | $0.05 |
Electricity Fees | $30,342 | - | $ | - |
Natural Gas | $40,696 | 6,004 | MMBtu | $6.78 |
TOTAL ENERGY COSTS | $523,395 | |||
RECOMMENDED SAVINGS* | $63,069 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $9,639 Cost: - |
- | - | - | - | - | - | - | - | $9,639 | - |
- - kWh |
- - $ |
- - lb |
- - $ |
$9,639 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8112 COMBINE UTILITY METERS |
Savings: $1,117 Cost: - |
- | - | - | - | - | - | - | - | $1,117 | - |
- - kWh |
- - $ |
- - lb |
- - $ |
$1,117 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8112 COMBINE UTILITY METERS |
Savings: $7,755 Cost: - |
- | - | - | - | - | - | - | - | $7,755 | - |
- - kWh |
- - $ |
- - lb |
- - $ |
$7,755 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4151 MINIMIZE WATER USAGE |
Savings: $113 Cost: - |
- | - | - | - | - | - | - | - | $113 | - |
- - kWh |
- - $ |
- - lb |
- - $ |
$113 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8112 COMBINE UTILITY METERS |
Savings: $375 Cost: - |
- | - | - | - | - | - | - | - | $375 | - |
- - kWh |
- - $ |
- - lb |
- - $ |
$375 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4155 METER WASTE WATER |
Savings: $980 Cost: $400 |
- | - | - | - | - | - | - | - | $980 | - |
- - kWh |
- - $ |
- - lb |
- - $ |
$980 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $19,035 Cost: $5,000 |
$17,958 | 594,959 | $1,077 | - | - | - | - | - | - | - |
$17,958 594,959 kWh |
$1,077 - $ |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $3,250 Cost: $6,700 |
- | - | - | - | $3,250 | 50,000 | - | - | - | - |
- - kWh |
- - $ |
$3,250 50,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $10,805 Cost: $4,600 |
$10,193 | 337,632 | $612 | - | - | - | - | - | - | - |
$10,193 337,632 kWh |
$612 - $ |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $10,000 Cost: - |
- | - | - | - | - | - | $10,000 | - | - | - |
- - kWh |
- - $ |
- - lb |
$10,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $63,069 Cost: $16,700 |
$28,151 | 932,591 | $1,689 | - | $3,250 | 50,000 | $10,000 | - | $19,979 | - | $28,151 932,591 kWh |
$1,689 - $ |
$3,250 50,000 lb |
$10,000 - $ |
$19,979 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - $ |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |