IAC logo
IAC Assessment: GT0714
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0714
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 2001
Principal Product Printed Towels
NAICS n/a
SIC 2396 - Automotive And Apparel Trimmings
Sales $1,000,000-$5,000,000
# of Employees 50
Plant Area (Sq.Ft.) 400,000
Annual Production 2,524,180 Pieces
Production Hrs. Annual 2,000
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $28,597 522,320 kWh $0.05
Electricity Demand $17,256 2,761 kW-months/year $6.25
Electricity Fees $1,825 - $ -
Natural Gas $95,727 12,527 MMBtu $7.64
TOTAL ENERGY COSTS $196,430
RECOMMENDED SAVINGS* $136,481 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $98,750
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes Water Consumption Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes Water Consumption
$ kWh $ kW-months/year $ $ $ MMBtu $ Tgal $ $ $ Tgal
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$630
Cost:
$250
$351 6,412 $244 39 $35 - - - - - - - - - $351
6,412
kWh
$244
39
kW-months/year
$35
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
Tgal
02: 3.4151 MINIMIZE WATER USAGE Savings:
$26,061
Cost:
$350
- - - - - - - - $25,650 135,000 - - $411 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$25,650
135,000
Tgal
-
-
$
$411
-
Tgal
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$10,570
Cost:
-
- - - - $10,570 - - - - - - - - - -
-
kWh
-
-
kW-months/year
$10,570
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
Tgal
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,100
Cost:
$138
$763 13,938 $275 44 $62 - - - - - - - - - $763
13,938
kWh
$275
44
kW-months/year
$62
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
Tgal
05: 4.1140 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS Savings:
$98,120
Cost:
$175,000
- - - - - - $38,120 4,990 - - $60,000 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$38,120
4,990
MMBtu
-
-
Tgal
$60,000
-
$
-
-
Tgal
TOTAL RECOMMENDED Savings:
$136,481
Cost:
$175,738
$1,114 20,350 $519 83 $10,667 - $38,120 4,990 $25,650 135,000 $60,000 - $411 - $1,114
20,350
kWh
$519
83
kW-months/year
$10,667
-
$
$38,120
4,990
MMBtu
$25,650
135,000
Tgal
$60,000
-
$
$411
-
Tgal
TOTAL IMPLEMENTED Savings:
$98,750
Cost:
$175,250
$351 6,412 $244 39 $35 - $38,120 4,990 - - $60,000 - - - $351
6,412
kWh
$244
39
kW-months/year
$35
-
$
$38,120
4,990
MMBtu
-
-
Tgal
$60,000
-
$
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ Tgal $ $ $ Tgal
Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes Water Consumption Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes Water Consumption