Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Indiana University-Purdue University |
---|---|
Assessment Year | 2016 |
Principal Product | Wire Shelving/ Organizational Boards |
NAICS | 332618 - Other Fabricated Wire Product Manufacturing |
SIC | 3496 - Misc. Fabricated Wire Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 75 |
Plant Area (Sq.Ft.) | 630,000 |
Annual Production | 10,437,079 Pieces |
Production Hrs. Annual | 2,100 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $293,383 | 4,170,614 | kWh | $0.07 |
Electricity Demand | $62,042 | 17,726 | kW-months/year | $3.50 |
Electricity Fees | $9,689 | - | $ | - |
Natural Gas | $74,239 | 14,437 | MMBtu | $5.14 |
TOTAL ENERGY COSTS | $458,546 | |||
RECOMMENDED SAVINGS* | $15,489 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,105 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.454 MODIFY STARTUP/SHUTDOWN TIMES |
Savings: $2,912 Cost: - |
- | - | $2,912 | 832 | - | - |
- - kWh |
$2,912 832 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES |
Savings: $1,741 Cost: - |
$1,630 | 23,170 | $111 | 32 | - | - |
$1,630 23,170 kWh |
$111 32 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $170 Cost: $5 |
$132 | 1,883 | $38 | 11 | - | - |
$132 1,883 kWh |
$38 11 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $416 Cost: $3 |
$416 | 5,908 | - | - | - | - |
$416 5,908 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $215 Cost: $36 |
$215 | 3,061 | - | - | - | - |
$215 3,061 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,624 Cost: $683 |
$2,624 | 37,296 | - | - | - | - |
$2,624 37,296 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $839 Cost: $586 |
$794 | 11,288 | $45 | 13 | - | - |
$794 11,288 kWh |
$45 13 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $268 Cost: $240 |
$268 | 3,803 | - | - | - | - |
$268 3,803 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $113 Cost: $112 |
- | - | - | - | $113 | 22 |
- - kWh |
- - kW-months/year |
$113 22 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2426 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR |
Savings: $5,185 Cost: $9,768 |
- | - | - | - | $5,185 | 1,009 |
- - kWh |
- - kW-months/year |
$5,185 1,009 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,006 Cost: $2,156 |
$783 | 11,130 | $223 | 64 | - | - |
$783 11,130 kWh |
$223 64 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $15,489 Cost: $13,589 |
$6,862 | 97,539 | $3,329 | 951 | $5,298 | 1,031 | $6,862 97,539 kWh |
$3,329 951 kW-months/year |
$5,298 1,031 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,105 Cost: $12,080 |
$1,546 | 21,982 | $261 | 74 | $5,298 | 1,031 | $1,546 21,982 kWh |
$261 74 kW-months/year |
$5,298 1,031 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |