Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Indiana University-Purdue University |
---|---|
Assessment Year | 2021 |
Principal Product | Machined parts and PEO coated parts |
NAICS | 336415 - Guided Missile and Space Vehicle Propulsion Unit and Propulsion Unit Parts Manufacturing |
SIC | 3764 - Space Propulsion Units And Parts |
Sales | $5,000,000-$10,000,000 |
# of Employees | 41 |
Plant Area (Sq.Ft.) | 42,666 |
Annual Production | 4,680 Units |
Production Hrs. Annual | 4,940 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $76,556 | 2,102,097 | kWh | $0.04 |
Electricity Demand | $258,296 | 11,767 | kW-months/year | $21.95 |
Electricity Fees | $27,303 | - | $ | - |
Natural Gas | $3,477 | 426 | MMBtu | $8.16 |
TOTAL ENERGY COSTS | $376,431 | |||
RECOMMENDED SAVINGS* | $24,050 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $236 Cost: $35 |
$236 | 7,804 | - | - | - | - | - | - |
$236 7,804 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $80 Cost: $97 |
$80 | 2,634 | - | - | - | - | - | - |
$80 2,634 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $22,427 Cost: $10,500 |
- | - | - | - | $22,427 | - | - | - |
- - kWh |
- - kW-months/year |
$22,427 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $1,039 Cost: $1,254 |
$(-17) | (-559) | - | - | - | - | $1,056 | 129 |
$(-17) (-559) kWh |
- - kW-months/year |
- - $ |
$1,056 129 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $268 Cost: $867 |
$97 | 38,532 | $171 | 8 | - | - | - | - |
$97 38,532 kWh |
$171 8 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $24,050 Cost: $12,753 |
$395 | 48,412 | $171 | 8 | $22,427 | - | $1,056 | 129 | $395 48,412 kWh |
$171 8 kW-months/year |
$22,427 - $ |
$1,056 129 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |