Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1985 |
Principal Product | DISTILLED MONOGLYCERIDES |
NAICS | n/a |
SIC | 2099 - Food Preparations, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 70 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 10,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $171,279 | 2,845,838 | kWh | $0.06 |
Natural Gas | $198,196 | 60,562 | MMBtu | $3.27 |
Other Energy | $8,000 | 1,136 | MMBtu | $7.04 |
TOTAL ENERGY COSTS | $377,475 | |||
RECOMMENDED SAVINGS* | $133,182 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $29,517 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Other Energy | Electricity Usage | Natural Gas | Other Energy | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3413 BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT |
Savings: $93,873 Cost: $350,000 |
$126,426 | 2,100,528 | $(-32,553) | (-9,955) | - | - |
$126,426 2,100,528 kWh |
$(-32,553) (-9,955) MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $9,544 Cost: $3,342 |
$9,544 | 158,558 | - | - | - | - |
$9,544 158,558 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2223 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF |
Savings: $6,350 Cost: $2,500 |
$6,350 | 105,510 | - | - | - | - |
$6,350 105,510 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1394 REPLACE STEAM JETS ON VACUUM SYSTEM WITH ELECTRIC MOTOR DRIVEN VACUUM PUMPS |
Savings: $1,428 Cost: $2,000 |
$(-900) | (-14,947) | $2,328 | 712 | - | - |
$(-900) (-14,947) kWh |
$2,328 712 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $8,064 Cost: $2,200 |
- | - | $8,064 | 2,466 | - | - |
- - kWh |
$8,064 2,466 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $5,611 Cost: $1,200 |
- | - | $5,611 | 1,716 | - | - |
- - kWh |
$5,611 1,716 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $6,298 Cost: $1,200 |
- | - | $6,298 | 1,926 | - | - |
- - kWh |
$6,298 1,926 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $311 Cost: $187 |
- | - | $311 | 95 | - | - |
- - kWh |
$311 95 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $1,323 Cost: - |
$71 | 1,172 | $1,252 | 383 | - | - |
$71 1,172 kWh |
$1,252 383 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.8223 ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE |
Savings: $239 Cost: - |
- | - | - | - | $239 | 34 |
- - kWh |
- - MMBtu |
$239 34 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $141 Cost: $40 |
$141 | 2,345 | - | - | - | - |
$141 2,345 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $133,182 Cost: $362,669 |
$141,632 | 2,353,166 | $(-8,689) | (-2,657) | $239 | 34 | $141,632 2,353,166 kWh |
$(-8,689) (-2,657) MMBtu |
$239 34 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $29,517 Cost: $7,942 |
$9,544 | 158,558 | $19,973 | 6,108 | - | - | $9,544 158,558 kWh |
$19,973 6,108 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Other Energy | Electricity Usage | Natural Gas | Other Energy |