IAC Assessment: KU0247
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0247
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1988
Principal Product MEAT PROCESSING
NAICS n/a
SIC 2011 - Meat Packing Plants
Sales $10,000,000-$50,000,000
# of Employees 58
Plant Area (Sq.Ft.) 0
Annual Production 0 Units
Production Hrs. Annual 2,000
Location (State) KS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $88,195 2,075,029 kWh $0.04
Natural Gas $35,708 10,787 MMBtu $3.31
TOTAL ENERGY COSTS $123,903
RECOMMENDED SAVINGS* $5,326 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,584
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7251 REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF Savings:
$411
Cost:
$3,100
$411 9,672 - - - - $411
9,672
kWh
-
-
MMBtu
-
-
$
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,591
Cost:
-
- - $1,741 526 $(-150) - -
-
kWh
$1,741
526
MMBtu
$(-150)
-
$
03: 2.1222 INSTALL TURBULATORS Savings:
$1,010
Cost:
$350
- - $1,010 305 - - -
-
kWh
$1,010
305
MMBtu
-
-
$
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,305
Cost:
-
$1,305 42,497 - - - - $1,305
42,497
kWh
-
-
MMBtu
-
-
$
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$288
Cost:
-
- - $288 87 - - -
-
kWh
$288
87
MMBtu
-
-
$
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$331
Cost:
$55
$331 7,913 - - - - $331
7,913
kWh
-
-
MMBtu
-
-
$
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$390
Cost:
$705
$473 11,137 $(-83) (-25) - - $473
11,137
kWh
$(-83)
(-25)
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$5,326
Cost:
$4,210
$2,520 71,219 $2,956 893 $(-150) - $2,520
71,219
kWh
$2,956
893
MMBtu
$(-150)
-
$
TOTAL IMPLEMENTED Savings:
$4,584
Cost:
$1,055
$1,778 53,634 $2,956 893 $(-150) - $1,778
53,634
kWh
$2,956
893
MMBtu
$(-150)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes