Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1999 |
Principal Product | wood windows |
NAICS | n/a |
SIC | 2431 - Millwork |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 140,800 |
Annual Production | 47,500 Pieces |
Production Hrs. Annual | 2,100 |
Location (State) | NE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $30,758 | 1,070,926 | kWh | $0.03 |
Electricity Demand | $36,814 | 4,826 | kW-months/year | $7.63 |
Natural Gas | $29,584 | 6,383 | MMBtu | $4.63 |
TOTAL ENERGY COSTS | $74,245 | |||
RECOMMENDED SAVINGS* | $75,110 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $6,910 Cost: $8,800 |
$1,980 | 86,166 | $4,930 | 547 | - | - | - | - | - | - |
$1,980 86,166 kWh |
$4,930 547 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $900 Cost: $520 |
$290 | 12,603 | $610 | 68 | - | - | - | - | - | - |
$290 12,603 kWh |
$610 68 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $620 Cost: $730 |
- | - | - | - | $620 | 133 | - | - | - | - |
- - kWh |
- - kW-months/year |
$620 133 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $55,080 Cost: $1,380 |
- | - | - | - | - | - | $55,080 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$55,080 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.424 IMPROVE SPACE COMFORT CONDITIONING |
Savings: $11,600 Cost: $10,670 |
- | - | - | - | - | - | - | - | $11,600 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$11,600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $75,110 Cost: $22,100 |
$2,270 | 98,769 | $5,540 | 615 | $620 | 133 | $55,080 | - | $11,600 | - | $2,270 98,769 kWh |
$5,540 615 kW-months/year |
$620 133 MMBtu |
$55,080 - $ |
$11,600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Product |