Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Louisiana Tech |
---|---|
Assessment Year | 1984 |
Principal Product | STEEL CASTINGS |
NAICS | n/a |
SIC | 3325 - Steel Foundries, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 267 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 6,000 Tons |
Production Hrs. Annual | 2,340 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $664,901 | 10,852,872 | kWh | $0.06 |
Natural Gas | $268,840 | 62,193 | MMBtu | $4.32 |
TOTAL ENERGY COSTS | $933,741 | |||
RECOMMENDED SAVINGS* | $113,094 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $113,094 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1135 REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY |
Savings: $75,700 Cost: $1,000 |
- | - | $75,700 | 17,520 |
- - kWh |
$75,700 17,520 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $2,320 Cost: $332 |
- | - | $2,320 | 536 |
- - kWh |
$2,320 536 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $674 Cost: $1,525 |
- | - | $674 | 156 |
- - kWh |
$674 156 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $25,600 Cost: $15,000 |
$25,600 | - | - | - |
$25,600 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $8,800 Cost: $840 |
$8,800 | - | - | - |
$8,800 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $113,094 Cost: $18,697 |
$34,400 | - | $78,694 | 18,212 | $34,400 - kWh |
$78,694 18,212 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $113,094 Cost: $18,697 |
$34,400 | - | $78,694 | 18,212 | $34,400 - kWh |
$78,694 18,212 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |