IAC Assessment: LT0073
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LT0073
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Louisiana Tech
Assessment Year 1986
Principal Product BALL BEARING ASSEMBLIES
NAICS n/a
SIC 3562 - Ball And Roller Bearings
Sales $10,000,000-$50,000,000
# of Employees 400
Plant Area (Sq.Ft.) 0
Annual Production 1,800,000 Pieces
Production Hrs. Annual 6,240
Location (State) AR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $608,028 12,427,902 kWh $0.05
Natural Gas $224,342 53,689 MMBtu $4.18
TOTAL ENERGY COSTS $832,370
RECOMMENDED SAVINGS* $90,736 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $760
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,670
Cost:
$250
$1,670 70,340 - - - - $1,670
70,340
kWh
-
-
MMBtu
-
-
$
02: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE Savings:
$1,620
Cost:
-
$1,620 68,288 - - - - $1,620
68,288
kWh
-
-
MMBtu
-
-
$
03: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$760
Cost:
-
$760 32,239 - - - - $760
32,239
kWh
-
-
MMBtu
-
-
$
04: 2.6232 INSTALL SET-BACK TIMERS Savings:
$605
Cost:
$3,500
$605 15,533 - - - - $605
15,533
kWh
-
-
MMBtu
-
-
$
05: 3.5314 USE IN-PROCESS RECYCLING WHENEVER POSSIBLE Savings:
$3,840
Cost:
$3,500
- - - - $3,840 - -
-
kWh
-
-
MMBtu
$3,840
-
$
06: 2.2511 INSULATE BARE EQUIPMENT Savings:
$269
Cost:
$210
- - $269 64 - - -
-
kWh
$269
64
MMBtu
-
-
$
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$80,900
Cost:
$4,000
$110,000 2,039,859 $(-29,100) (-6,960) - - $110,000
2,039,859
kWh
$(-29,100)
(-6,960)
MMBtu
-
-
$
08: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$1,072
Cost:
$596
$583 24,619 $489 117 - - $583
24,619
kWh
$489
117
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$90,736
Cost:
$12,056
$115,238 2,250,878 $(-28,342) (-6,779) $3,840 - $115,238
2,250,878
kWh
$(-28,342)
(-6,779)
MMBtu
$3,840
-
$
TOTAL IMPLEMENTED Savings:
$760
Cost:
-
$760 32,239 - - - - $760
32,239
kWh
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes