IAC Assessment: LT8369
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LT8369
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Louisiana Tech
Assessment Year 2022
Principal Product Frozen meat pie
NAICS 311412 - Frozen Specialty Food Manufacturing
SIC 2038 - Frozen Specialties, Nec
Sales $10,000,000-$50,000,000
# of Employees 50
Plant Area (Sq.Ft.) 25,450
Annual Production 1,000,000 Pieces
Production Hrs. Annual 2,210
Location (State) LA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $99,508 1,310,694 kWh $0.08
Electricity Demand $83,284 5,566 kW-months/year $14.96
Electricity Fees $29,746 - $ -
Natural Gas $30,567 2,061 MMBtu $14.83
TOTAL ENERGY COSTS $243,105
RECOMMENDED SAVINGS* $31,876 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$12,717
Cost:
$30,030
$8,129 106,956 $4,588 307 - - $8,129
106,956
kWh
$4,588
307
kW-months/year
-
-
MMBtu
02: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$14,592
Cost:
$12,831
$11,493 151,219 $3,099 207 - - $11,493
151,219
kWh
$3,099
207
kW-months/year
-
-
MMBtu
03: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT Savings:
$4,568
Cost:
$3,852
- - - - $4,568 308 -
-
kWh
-
-
kW-months/year
$4,568
308
MMBtu
TOTAL RECOMMENDED Savings:
$31,876
Cost:
$46,713
$19,621 258,175 $7,687 514 $4,568 308 $19,621
258,175
kWh
$7,687
514
kW-months/year
$4,568
308
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas