Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Louisiana Tech |
---|---|
Assessment Year | 2025 |
Principal Product | Office Space |
NAICS | 531120 - Lessors of Nonresidential Buildings (except Miniwarehouses) |
SIC | 6512 - Nonresidential Building Operators |
Sales | $1,000,000-$5,000,000 |
# of Employees | 2 |
Plant Area (Sq.Ft.) | 68,000 |
Annual Production | 40 Units |
Production Hrs. Annual | 6,240 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $162,994 | 2,187,000 | kWh | $0.07 |
Electricity Demand | $46,170 | 9,845 | kW-months/year | $4.69 |
TOTAL ENERGY COSTS | $209,986 | |||
RECOMMENDED SAVINGS* | $10,068 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Usage | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Usage | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.126 INSTALL SENSORS TO DETECT DEFECTS |
Savings: $1,596 Cost: $616 |
- | - | - | - | $1,596 | 94 | - | - |
- - kWh |
- - kW-months/year |
$1,596 94 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $4,566 Cost: $2,288 |
$4,073 | 54,673 | $493 | 105 | - | - | - | - |
$4,073 54,673 kWh |
$493 105 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,416 Cost: $1,302 |
$3,166 | 42,495 | $273 | 58 | - | - | $(-22) | - |
$3,166 42,495 kWh |
$273 58 kW-months/year |
- - Tgal |
$(-22) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE |
Savings: $490 Cost: $250 |
$370 | 4,967 | $119 | 25 | - | - | - | - |
$370 4,967 kWh |
$119 25 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,068 Cost: $4,456 |
$7,609 | 102,136 | $886 | 189 | $1,596 | 94 | $(-22) | - | $7,609 102,136 kWh |
$886 189 kW-months/year |
$1,596 94 Tgal |
$(-22) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Usage | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Usage | Ancillary Material Cost |