Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1989 |
Principal Product | AEROSOL & STICK SOLIDS |
NAICS | n/a |
SIC | 2844 - Toilet Preparations |
Sales | $10,000,000-$50,000,000 |
# of Employees | 450 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 110,000 Thousand Gallons |
Production Hrs. Annual | 4,420 |
Location (State) | RI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $495,371 | 5,720,399 | kWh | $0.09 |
LPG | $1,770 | 152 | MMBtu | $11.64 |
Fuel Oil #6 | $128,935 | 50,981 | MMBtu | $2.53 |
TOTAL ENERGY COSTS | $626,076 | |||
RECOMMENDED SAVINGS* | $32,332 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $335 |
#|Description |
Savings Cost |
Status | Electricity Usage | LPG | Fuel Oil #6 | Administrative Changes | Electricity Usage | LPG | Fuel Oil #6 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $335 Cost: $703 |
- | - | - | - | $335 | 132 | - | - |
- - kWh |
- - MMBtu |
$335 132 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $476 Cost: $1,254 |
$562 | 7,034 | - | - | $(-86) | (-34) | - | - |
$562 7,034 kWh |
- - MMBtu |
$(-86) (-34) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3413 BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT |
Savings: $30,146 Cost: $123,000 |
$39,108 | 412,368 | - | - | $(-7,962) | (-3,147) | $(-1,000) | - |
$39,108 412,368 kWh |
- - MMBtu |
$(-7,962) (-3,147) MMBtu |
$(-1,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,375 Cost: $3,000 |
$3,140 | 38,980 | $(-1,765) | (-152) | - | - | - | - |
$3,140 38,980 kWh |
$(-1,765) (-152) MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,332 Cost: $127,957 |
$42,810 | 458,382 | $(-1,765) | (-152) | $(-7,713) | (-3,049) | $(-1,000) | - | $42,810 458,382 kWh |
$(-1,765) (-152) MMBtu |
$(-7,713) (-3,049) MMBtu |
$(-1,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $335 Cost: $703 |
- | - | - | - | $335 | 132 | - | - | - - kWh |
- - MMBtu |
$335 132 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | LPG | Fuel Oil #6 | Administrative Changes | Electricity Usage | LPG | Fuel Oil #6 | Administrative Changes |