Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1997 |
Principal Product | high quality converted papers |
NAICS | n/a |
SIC | 2672 - Paper Coated And Laminated, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 101 |
Plant Area (Sq.Ft.) | 310,000 |
Annual Production | 20,000,000 Pounds |
Production Hrs. Annual | 5,880 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $291,467 | 5,038,101 | kWh | $0.06 |
Electricity Demand | $148,862 | 13,975 | kW-months/year | $10.65 |
Natural Gas | $13,984 | 3,024 | MMBtu | $4.62 |
Fuel Oil #2 | $124,228 | 24,065 | MMBtu | $5.16 |
TOTAL ENERGY COSTS | $588,701 | |||
RECOMMENDED SAVINGS* | $22,295 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,507 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Other Liquid (haz) | Solid Waste (haz) | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Other Liquid (haz) | Solid Waste (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | gal | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.4145 USE MAGNETIC TECHNOLOGY TO TREAT WATER |
Savings: $7,580 Cost: $9,347 |
- | - | - | - | - | - | - | - | $3,790 | 124 | $3,790 | 3,944 |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$3,790 124 gal |
$3,790 3,944 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) |
Savings: $5,492 Cost: $11,700 |
- | - | - | - | $2,746 | 459 | $2,746 | 459 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,746 459 MMBtu |
$2,746 459 MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2612 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION |
Savings: $4,207 Cost: $14,329 |
$4,207 | 67,702 | - | - | - | - | - | - | - | - | - | - |
$4,207 67,702 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,606 Cost: $75 |
$2,606 | 44,842 | - | - | - | - | - | - | - | - | - | - |
$2,606 44,842 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $1,409 Cost: $60 |
$947 | 15,240 | $462 | 47 | - | - | - | - | - | - | - | - |
$947 15,240 kWh |
$462 47 kW-months/year |
- - MMBtu |
- - MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $819 Cost: $102 |
$819 | 13,189 | - | - | - | - | - | - | - | - | - | - |
$819 13,189 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $182 Cost: $132 |
$182 | 2,931 | - | - | - | - | - | - | - | - | - | - |
$182 2,931 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,295 Cost: $35,745 |
$8,761 | 143,904 | $462 | 47 | $2,746 | 459 | $2,746 | 459 | $3,790 | 124 | $3,790 | 3,944 | $8,761 143,904 kWh |
$462 47 kW-months/year |
$2,746 459 MMBtu |
$2,746 459 MMBtu |
$3,790 124 gal |
$3,790 3,944 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,507 Cost: $11,835 |
$3,553 | 60,082 | $462 | 47 | $2,746 | 459 | $2,746 | 459 | - | - | - | - | $3,553 60,082 kWh |
$462 47 kW-months/year |
$2,746 459 MMBtu |
$2,746 459 MMBtu |
- - gal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | gal | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Other Liquid (haz) | Solid Waste (haz) | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Other Liquid (haz) | Solid Waste (haz) |