IAC Assessment: MA0410
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0410
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1998
Principal Product Tissue paper
NAICS n/a
SIC 2676 - Sanitary Paper Products
Sales n/a
# of Employees 28
Plant Area (Sq.Ft.) 200,000
Annual Production 24,000,000 Pounds
Production Hrs. Annual 6,000
Location (State) NH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $126,710 1,412,075 kWh $0.09
Electricity Demand $28,555 3,449 kW-months/year $8.28
Fuel Oil #6 $98,163 26,669 MMBtu $3.68
TOTAL ENERGY COSTS $253,428
RECOMMENDED SAVINGS* $41,882 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #6 Administrative Changes Electricity Usage Fuel Oil #6 Administrative Changes
$ kWh $ MMBtu $ $
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$8,484
Cost:
$7,225
$8,484 95,838 - - - - $8,484
95,838
kWh
-
-
MMBtu
-
-
$
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$16,796
Cost:
$11,700
$16,796 189,625 - - - - $16,796
189,625
kWh
-
-
MMBtu
-
-
$
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$5,014
Cost:
$4,925
$5,014 56,565 - - - - $5,014
56,565
kWh
-
-
MMBtu
-
-
$
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$5,403
Cost:
$4,925
$5,403 60,961 - - - - $5,403
60,961
kWh
-
-
MMBtu
-
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,895
Cost:
$3,400
$1,895 21,395 - - - - $1,895
21,395
kWh
-
-
MMBtu
-
-
$
06: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$2,746
Cost:
-
- - - - $2,746 - -
-
kWh
-
-
MMBtu
$2,746
-
$
07: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE Savings:
$1,030
Cost:
$236
- - $1,030 312 - - -
-
kWh
$1,030
312
MMBtu
-
-
$
08: 2.2511 INSULATE BARE EQUIPMENT Savings:
$514
Cost:
$626
- - $514 156 - - -
-
kWh
$514
156
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$41,882
Cost:
$33,037
$37,592 424,384 $1,544 468 $2,746 - $37,592
424,384
kWh
$1,544
468
MMBtu
$2,746
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Fuel Oil #6 Administrative Changes Electricity Usage Fuel Oil #6 Administrative Changes