IAC Assessment: MA0423
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0423
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1998
Principal Product Airport Lighting
NAICS n/a
SIC 3648 - Lighting Equipment, Nec
Sales $10,000,000-$50,000,000
# of Employees 130
Plant Area (Sq.Ft.) 66,000
Annual Production 50,000 Pieces
Production Hrs. Annual 2,080
Location (State) CT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $66,197 1,013,482 kWh $0.07
Electricity Demand $32,858 3,650 kW-months/year $9.00
Natural Gas $17,748 2,442 MMBtu $7.27
TOTAL ENERGY COSTS $116,803
RECOMMENDED SAVINGS* $12,190 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,575
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$3,806
Cost:
$300
- - - - $3,806 488 -
-
kWh
-
-
kW-months/year
$3,806
488
MMBtu
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$4,841
Cost:
$2,700
$2,387 37,515 $3,702 432 $(-1,248) (-160) $2,387
37,515
kWh
$3,702
432
kW-months/year
$(-1,248)
(-160)
MMBtu
03: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$1,343
Cost:
$234
$1,343 21,102 - - - - $1,343
21,102
kWh
-
-
kW-months/year
-
-
MMBtu
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$1,279
Cost:
$80,000
$951 14,947 $827 86 $(-499) (-64) $951
14,947
kWh
$827
86
kW-months/year
$(-499)
(-64)
MMBtu
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$585
Cost:
$2,627
- - - - $585 75 -
-
kWh
-
-
kW-months/year
$585
75
MMBtu
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$187
Cost:
$294
$187 2,931 - - - - $187
2,931
kWh
-
-
kW-months/year
-
-
MMBtu
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$149
Cost:
$257
$149 2,345 - - - - $149
2,345
kWh
-
-
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$12,190
Cost:
$86,412
$5,017 78,840 $4,529 518 $2,644 339 $5,017
78,840
kWh
$4,529
518
kW-months/year
$2,644
339
MMBtu
TOTAL IMPLEMENTED Savings:
$10,575
Cost:
$5,861
$3,730 58,617 $3,702 432 $3,143 403 $3,730
58,617
kWh
$3,702
432
kW-months/year
$3,143
403
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas