Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1999 |
Principal Product | Printed Household Items |
NAICS | n/a |
SIC | 2392 - Housefurnishings, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 120,000 |
Annual Production | 3,500,000 Pieces |
Production Hrs. Annual | 2,250 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $45,568 | 684,349 | kWh | $0.07 |
Electricity Demand | $8,523 | 2,348 | kW-months/year | $3.63 |
Electricity Fees | $807 | - | $ | - |
Natural Gas | $40,799 | 6,403 | MMBtu | $6.37 |
TOTAL ENERGY COSTS | $115,053 | |||
RECOMMENDED SAVINGS* | $8,229 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,545 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.4157 REPLACE WATER COOLING ON PROCESSES WITH AIR COOLING |
Savings: $4,467 Cost: $7,563 |
- | - | - | - | - | - | $2,983 | 391,555 | $1,484 | 90 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,983 391,555 Tgal |
$1,484 90 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,793 Cost: $6,075 |
$1,597 | 23,740 | $196 | 54 | - | - | - | - | - | - |
$1,597 23,740 kWh |
$196 54 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $999 Cost: $480 |
- | - | - | - | $999 | 180 | - | - | - | - |
- - kWh |
- - kW-months/year |
$999 180 MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $891 Cost: $400 |
- | - | - | - | $891 | 161 | - | - | - | - |
- - kWh |
- - kW-months/year |
$891 161 MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $79 Cost: $35 |
$79 | 1,172 | - | - | - | - | - | - | - | - |
$79 1,172 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,229 Cost: $14,553 |
$1,676 | 24,912 | $196 | 54 | $1,890 | 341 | $2,983 | 391,555 | $1,484 | 90 | $1,676 24,912 kWh |
$196 54 kW-months/year |
$1,890 341 MMBtu |
$2,983 391,555 Tgal |
$1,484 90 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,545 Cost: $8,078 |
$79 | 1,172 | - | - | $999 | 180 | $2,983 | 391,555 | $1,484 | 90 | $79 1,172 kWh |
- - kW-months/year |
$999 180 MMBtu |
$2,983 391,555 Tgal |
$1,484 90 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) |