Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2001 |
Principal Product | Paper |
NAICS | n/a |
SIC | 2621 - Paper Mills |
Sales | $50,000,000-$100,000,000 |
# of Employees | 225 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 40,000 Tons |
Production Hrs. Annual | 8,600 |
Location (State) | VT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,631,300 | 33,006,478 | kWh | $0.05 |
Electricity Demand | $558,531 | 61,285 | kW-months/year | $9.11 |
Electricity Fees | $49,571 | - | $ | - |
Fuel Oil #2 | $157,800 | 19,991 | MMBtu | $7.89 |
Fuel Oil #6 | $1,586,800 | 384,636 | MMBtu | $4.13 |
TOTAL ENERGY COSTS | $3,984,002 | |||
RECOMMENDED SAVINGS* | $420,825 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $135,125 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #6 | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Fuel Oil #6 | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $241,800 Cost: $250,000 |
$(-25,600) | (-513,200) | $(-6,600) | (-720) | $274,000 | 66,450 | - | - | - | - |
$(-25,600) (-513,200) kWh |
$(-6,600) (-720) kW-months/year |
$274,000 66,450 MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $84,500 Cost: $1,500 |
- | - | - | - | $84,500 | 20,500 | - | - | - | - |
- - kWh |
- - kW-months/year |
$84,500 20,500 MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.4151 MINIMIZE WATER USAGE |
Savings: $25,000 Cost: - |
- | - | - | - | - | - | - | - | $25,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$25,000 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4141 REPLACE THE CHLORINATION STAGE WITH AN OXYGEN OR OZONE STAGE |
Savings: $24,500 Cost: $5,000 |
- | - | - | - | - | - | $(-13,500) | - | $38,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$(-13,500) - $ |
$38,000 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $10,500 Cost: $20,000 |
$10,500 | 211,000 | - | - | - | - | - | - | - | - |
$10,500 211,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,025 Cost: $700 |
$6,025 | 120,500 | - | - | - | - | - | - | - | - |
$6,025 120,500 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,800 Cost: - |
$5,800 | 116,000 | - | - | - | - | - | - | - | - |
$5,800 116,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,000 Cost: $12,000 |
$5,000 | 99,000 | - | - | - | - | - | - | - | - |
$5,000 99,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,900 Cost: $8,000 |
$4,900 | 97,400 | - | - | - | - | - | - | - | - |
$4,900 97,400 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,700 Cost: $7,500 |
$3,700 | 74,000 | - | - | - | - | - | - | - | - |
$3,700 74,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,000 Cost: $8,000 |
$3,000 | 60,500 | - | - | - | - | - | - | - | - |
$3,000 60,500 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,000 Cost: $8,000 |
$3,000 | 62,500 | - | - | - | - | - | - | - | - |
$3,000 62,500 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,900 Cost: $1,000 |
$2,900 | 57,700 | - | - | - | - | - | - | - | - |
$2,900 57,700 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $200 Cost: $150 |
- | - | - | - | $200 | 48 | - | - | - | - |
- - kWh |
- - kW-months/year |
$200 48 MMBtu |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $420,825 Cost: $321,850 |
$19,225 | 385,400 | $(-6,600) | (-720) | $358,700 | 86,998 | $(-13,500) | - | $63,000 | - | $19,225 385,400 kWh |
$(-6,600) (-720) kW-months/year |
$358,700 86,998 MMBtu |
$(-13,500) - $ |
$63,000 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $135,125 Cost: $29,850 |
$25,425 | 506,900 | - | - | $84,700 | 20,548 | - | - | $25,000 | - | $25,425 506,900 kWh |
- - kW-months/year |
$84,700 20,548 MMBtu |
- - $ |
$25,000 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #6 | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Fuel Oil #6 | Ancillary Material Cost | Water Consumption |